GOVERNMENT OF NCT OF DELHI Vs. SUDESH VERMA
LAWS(SC)-2022-12-12
SUPREME COURT OF INDIA (FROM: DELHI)
Decided on December 02,2022

GOVERNMENT OF NCT OF DELHI Appellant
VERSUS
SUDESH VERMA Respondents




JUDGEMENT

M.R.SHAH,J. - (1.)Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 5258 of 2015 by which the High Court has allowed the said writ petition and has declared that the land acquisition proceedings under the Land Acquisition Act, 1894 (hereinafter referred to as 'Act, 1894') with regard to the land in question is deemed to have lapsed under Sec. 24(2) of the Right to Fair Compensation and Transparency in Land cquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter erred to as 'Act, 2013'), the Government of NCT of Delhi and Anr. have preferred the present appeal.
(2.)From the impugned judgment and order passed by the High Court, it appears that while declaring that the acquisition proceedings under the Act, 1894 is deemed to have lapsed under Sec. 24(2) of the Act, 2013, the High Court has heavily relied upon the decision of this Court in the case of Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183.
2.1 However, the High Court has failed to notice and consider the specific case on behalf of the appellants that at the relevant time, the possession could not be taken over due to the pending proceedings at the instance of the landowners challenging the acquisition proceedings, which ended upto this Court. The original landowners failed in challenge to the acquisition proceedings upto this Court. Under the circumstances, when due to pendency of the land acquisition proceedings, the possession could not be taken over, thereafter, it will not be open for the landowners to contend that as the possession was not taken over, the land acquisition proceedings be deemed to have lapsed under Sec. 24(2) of the Act, 2013.

2.2 In the case of Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129, in paragraph 366, the Constitution Bench of this Court has observed and held as under:-

'366. In view of the aforesaid discussion, we answer the questions as under:

366.1. Under the provisions of Sec. 24(1)(a) in case the award is not made as on 1/1/2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act.

366.2. In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Sec. 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed.

366.3. The word 'or' used in Sec. 24(2) between possession and compensation has to be read as 'nor' or as 'and'. The deemed lapse of land acquisition proceedings under Sec. 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.

366.4. The expression 'paid' in the main part of Sec. 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Sec. 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Sec. 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Sec. 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Sec. 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the 'landowners' as on the date of notification for land acquisition under Sec. 4 of the 1894 Act.

366.5. In case a person has been tendered the compensation as provided under Sec. 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Sec. 24(2) due to non-payment or non- deposit of compensation in court. The obligation to pay is complete by tendering the amount under Sec. 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Sec. 24(2) of the 2013 Act.

366.6. The proviso to Sec. 24(2) of the 2013 Act is to be treated as part of Sec. 24(2), not part of Sec. 24(1)(b).

366.7. The mode of taking possession under the 1894 Act and as contemplated under Sec. 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Sec. 16 of the 1894 Act, the land vests in State there is no divesting provided under Sec. 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Sec. 24(2).

366.8. The provisions of Sec. 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1/1/2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years.

366.9. Sec. 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Sec. 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1/1/2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.'

(3.)In view of the above and for the reasons stated above, the impugned judgment and order passed by the High Court declaring that the land acquisition proceedings with respect to the land in question has lapsed under Sec. 24(2) of the Act, 2013 is unsustainable and the same deserves to be quashed and set aside and is accordingly quashed and set aside.
Present appeal is accordingly allowed. No costs.

Pending application(s), if any, also stand(s) disposed of.

;


Click here to view full judgement.