JUDGEMENT
K.SAMPATH, J. -
(1.) The Opposite party in COP No.277/2000 on the file of the District
Consumer Disputes Redressal Forum, Coimbatore is the appellant herein.
The case of the complainant was as follows: - There was an agreement
entered into between the complainant and the Opposite party on 20/10/97
for construction of a house for the complainant by the opposite party.
The agreement provided that the building should be completed within a
period of three months. The Opposite party took one year and for the
extra work the complainant had to make payment. In the site there was a
small old building in existence and as per the agreement, four feet earth
work had to be undertaken for the foundation. Instead of laying the
foundation for the whole area, the opposite party left the old building
as it was constructed and on the very same foundation put up construction
with lime and sand without using cement. While the construction was in
progress, the complainant raised objections but the opposite party
assured the complainant that he would raise pillars to give support to
the old building, but he did not do that. As a result, a major crack
developed in the building and it was likely to damage the entire
construction. The opposite party left the building incomplete, without
plastering, without even constructing a compound wall, painting, etc, and
handed over the building sometime in October 1999. The complainant had to
engage another builder and complete the pending works spending
Rs.20,000/-. The complainant was worried about the old structure as a
major crack had developed and it would collapse if the foundation or
protection by raising the pillars was not done within a short span. A sum
of Rs.1 lakh would be needed by the complainant for doing that work. The
complainant had paid extra amount of Rs.57,000/- to the opposite party
instead of Rs.3,25,000/- as agreed. Septic tank, compound wall and sump
which were not shown in the drawing had to be done and a sum of
Rs.51,000/- was incurred for that purpose. Still, the opposite party was
left with Rs.6,000/- extra. The complainant sent a notice. The opposite
party sent a reply claiming extra cost which was not tenable. In these
circumstances, the complaint came to be filed for a direction to the
opposite party to destroy the structure constructed on the old structure
and to lay new foundation as per the agreement and re-construct the
building or order payment of Rs.1 lakh so as to enable the complainant to
reconstruct that portion, to refund the extra amount of Rs.6,000/-, to
pay Rs.20,000/- for the incomplete work, Rs.20,000/- towards mental
agony, Rs.2,000/- towards expenses for the complaint and Rs.1,000/- to
meet the Commissioners fees in case a Commissioner was appointed.
(2.) The Opposite party filed a version disputing the various allegations
and further stating as follows: - The complainant had already constructed
240 Sq.ft. of building upto the lintel level. The additional and excess
work not covered by the agreement carried out by the opposite party
involved Rs.1,05,965/- viz., for compound wall, underground water tank,
septic tank and portico and staircase. This amount the complainant was
liable to pay to the opposite party. The opposite party did not undertake
to demolish the old construction and put up a new structure with
foundation of four feet. Any defect in the old building could not be
attributed to the opposite party. It was not correct to say that major
cracks had developed in the building. The delay in the construction of
the building was due to delay in payment by the complainant. It was not
correct to say that the complainant engaged another builder for
completing the incomplete works. There was no basis for the
complainants apprehension that the old structure had developed cracks
and it would collapse. The alleged crack was not due to any defect in the
construction by the opposite party. There was no excess payment made by
the complainant. The complainant had forcibly entered the premises
without the consent and knowledge of the opposite party. Materials worth
Rs.7,400/- were kept in the premises. That amount was payable by the
complainant. The opposite party had put up construction to the tune of
Rs.4,30,965/- including a sum of Rs.1,05,965/- for the additional and
extra works. The complainant had paid only Rs.3,82,000/- and there was a
balance of Rs.48,965/- apart from Rs.7,400/- being the value of the
building materials left in the premises. The complaint was liable to be
dismissed.
(3.) Before the District Forum, on the side of the complainant Exs.A-1 to
A-5 were marked while on the side of the opposite party no document was
marked. There was a Commissioner appointed who inspected the property and
filed report which was marked as Ex.C-1.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.