JUDGEMENT
A.K.ANNAMALAI, J. -
(1.) The complaint filed under Section 17 of the Consumer Protection Act 1986
The complainant filed a complaint against the opposite parties 1 to 3
pray for the reliefs of direction to pay Rs.3,19,000/- towards rent paid
by the flat owners before taking possession of the flats from the
opposite parties to pay Rs.8,19,800/- towards the cost and expenses
incurred for repair and completion of unfinished work in respective flats
and in common areas, to pay Rs.5,00,000/- for the loss a life of one
Mr.P.S.Loganathan due to the negligence in failing to cover the naked
wire to pay Rs.10,00,000/- for deficiency of service by the opposite
parties failing to construct and hand over flats as per construction
agreement to pay Rs.10,00,000/- as compensation for mental agony, pain
and loss suffered and to pay Rs.25,000/- towards cost.
(2.) The brief case of the complainant as stated in the complaint is as
follows:- The complainants are the Owners and Member in Resident Welfare
Association represented by its President and the allottees of the flats
were constructed by the opposite parties on the basis of respective
construction agreement and purchased from the opposite parties. The 1st
opposite party who agreed to complete the construction within the
stipulated period, but not completed within time and failed to hand over
the flats to the owners and the delay caused undue hardship to the flat
owners of flats Nos.G1, F2, S1, S3, T2 and T3 to pay additional rent for
their stay to the extent of Rs.3,19,000/- as mentioned each amount in the
complaint and the opposite parties issued possession certificate which is
not seems to be a genuine one and not providing the lift for the use of
allottees as per the agreement caused much difficulties and agony to
negotiate three floors without the use of lift and there also the
opposite parties failed to provide various connected facilities and there
are defects in the walls of the flats and they are incomplete with full
of putty and bubbles and all the defects are rectified by spending
additional costs to the extent of Rs.4,54,500/- as the claim of
association for common area and another sum of Rs.1,08,800/- for various
repairs relating to the flat owners including repairs of doors plumbing
work, rechecking of electrical installation, labour charges, change over
switches, etc., and various sums to the flat owners to the extent of
Rs.8,19,800/- including the common area cost. Further one Loganathan,
father of the flat F1 owner Sankarasubramaniam died on 24.1.05 when they
were in the flat after the house warming function and on that date when
he had opened the rear side compound gate to receive the visitor due to
the electric shock on the gate because of naked wire he died for which a
legal notice was sent on 18th May 2006 and the bald reply was sent on
27.5.06. All the members of the complainant association who are the
respective flat owners are put to great hardship and mental agony by the
1st opposite party due to its lethargic attitude of not attending to the
incomplete constructions and not honoring several clauses in the
construction agreement and even though admitted to rectify the defects by
way of reply letters but not acted upon. Thus the acts of opposite
parties in failing to perform as agreed in accordance with the
construction agreement leading to loss of life, additional expenditure to
carry out incomplete works are all amounts to deficiency of service and
thereby the complainants are claiming the various amounts as stated above.
(3.) The 1st opposite party filed written version which are adopted by the
other and in the written version on behalf of the opposite parties they
denied the allegations of complainant and regarding the payment of claim
for rents by flat owners G1, F2, S1, S3, T2, T3, it is stated that all
those owners are all irregular in their payment of electricity deposits
construction cost etc., and thereby there was a delay in handing over the
flats for which the opposite parties are not to pay any loss of rent.
Further regarding the other allegations relating to the defective
constructions materials non provision of facilities etc., it is stated by
the opposite parties the delayed payment of allottees unethical attitude
of the one of the allottees F1 with whom the opposite party entered joint
venture agreement delayed payment of EB deposit by sum of the allottees
etc., and additional works asked for by the allottees have resulted in
untold misery to the opposite party and in spite of the same they have
done everything within the realm of possibility and under their control
to complete the construction in accordance with the construction
agreement and handed over possession of the flats. The delay is not due
to the opposite parties but were solely due to the irregular and delayed
payments on the part of the allottees additional work such as carpentry
work sought by the allottees and the land owner and the allottee of flat
F1 in order to get escalated payment from the opposite parties
deliberately delayed the execution of sale deed for undivided shares for
some of the allottees and as such no delay can be attributed to the
opposite parties. Further the opposite party committed to install the
lift but was obstructed by the complainant to do the same and this
opposite party undertakes to complete the same, if the complainants
association is directed not to obstruct the work. Regarding the death of
the Loganathan, the opposite party in no way connected as the occurrence
took place on 24.1.05 and there was no such complaint even prior to the
death from 13.1.05 on the date of occupation and the newspaper report
certifies that the accident was because of touching the nacked live wire
of the decorative lamp which was not installed by the opposite parties.
Hence the complaint deserves to be dismissed.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.