JUDGEMENT
M.THANIKACHALAM J. -
(1.) The appellant as complainant filed a complaint before the District Forum
against the respondent/opposite party praying for the direction to the
opposite party to deliver the constructed flat as agreed in the
agreement, to pay Rs.1,05,000/- towards the delay of 42 months as agreed
in the agreement, to pay Rs.10,000/- towards mental agony and to pay
Rs.15,000/- towards deficiency in service. The District Forum dismissed
the complaint, against the said order, this appeal is preferred praying
to set aside the order of the District Forum dt.10.02.2009 in C.C.19/2003.
This appeal coming before us for hearing finally on 05.04.2011, upon
hearing the arguments of the either counsels and perused the documents,
as well as the order of the District Forum, this Commission made the
following order:
The complainant having failed before the District Forum to get the
desired order, has come to this Commission as appellant for redressal.
(2.) The complainant entered into a construction agreement, on 03.11.98
with the opposite party, who had agreed to construct and hand over a flat
in the ground floor, measuring 900 sq.ft. in Survey No.255/2A in Plot
No.65/2, for which, he had received consideration also, acknowledged in
the construction agreement itself. As agreed, the opposite party had not
handed over the constructed flat, within the stipulated time namely
within three months from 18.11.98 on which date possession of the land
was given after registration of the undivided share. It was also agreed
that the opposite party shall pay to the complainant, a compensation of
Rs.2,500/- per month in case of failure to deliver the possession, within
the said time. Despite lawyers notice, repeated demands since the
opposite party failed to deliver the constructed flat, he has committed
deficiency, causing mental agony, for which, direction should be issued
against them, to deliver the constructed flat as well directing them to
pay compensation as catalogued, in Para 10 of the complaint.
(3.) The opposite party not admitting either the construction agreement or
the payment of consideration, opposed the claim, contending that though
there was a memorandum of agreement dated 03.1198, drafted, not agreed by
the parties cannot be enforced, that the complainant has not paid a sum
of Rs.6 lakhs as falsely alleged and recited in the incomplete document,
that since there was no valid agreement between the parties for
construction of the flat and handing over, supported by consideration the
non-delivery of the flat, cannot be construed as negligent act or
deficiency in service, praying for the dismissal of the complaint.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.