JUDGEMENT
A.K.ANNAMALAI, J. -
(1.) The complaint filed under Section 17 of the Consumer Protection Act-
1986 :
Complainant is a 5 Star Hotel having his brand name Lee Royal Meridian,
Chennai and in the hotel premises at No.1, GST Road, Saint Thomas Mount
for the purpose of water producing by Reverse Osmosis Plant for the use
of the complainant. The opposite party at the cost of the complainant,
supplied, installed and commissioned the plant and thereafter it was
entrusted for maintenance under an agreement contract dated 26.9.06 for
the period from 26.9.06 to 25.10.08 on monthly charges of Rs.25,000/- and
as per the contract the opposite party agreed to operate the R.O. Plant
for 3 shifts deputing skilled operator for one shift and to maintain all
log books and records with supervision once in a month and the Engineer
to visit once in 15 days and before the performance of the R.O to the
complainant. During the 2nd week of February 2007 when the engineer
inspected the R.O Plant found out the permeate flow is dropped down to 80
LPM and the log book was not maintained by the opposite party. On the
advise of opposite party the membrane cleaning was made and in spite of
that cleaning no improvement was made in the water flow and during the
September 2008 when the Engineer of the complainant inspected the R.O
plant found the permeate flow is dropped down to 8- LPM there was leakage
in the pipelines and the high pressure pump set water hardness was 50 PPM
was very much above the expected limit which would affect the performance
of the equipments of the R.O. Plant. Consequent to the improper
maintenance other equipments like boilers imported kitchen equipments
also damaged. Apart from the maintenance charges of Rs.25,000/- every
month paid till May 2008 as per the suggestion of the Area Manager of the
opposite party another sum of Rs.60,000/- was spent to improve the flow
rate but was not achieved. Hence a legal notice was issued on 20.10.2008
for the refund of amount paid for the service charges amounting
Rs.5,00,000/- together with Rs.25,00,000/- being the damages to the R.O
plant and other equipments for which a false reply was received was by
the opposite party on 6.11.08 demanding Rs.1,51,735/- being the
maintenance charges and cost of spare parts. Hence the complainant filed
this complaint claiming to refund the sum of Rs.5,00,000/- being the
total operation and maintenance charges received from the complainant to
pay a sum of Rs.25,00,000/- to the complainant towards damages to the R.O
plant and other equipments and Rs.50,000/- towards compensation for
mental agony and for costs.
(2.) The opposite party denied the allegations of the complainant in their
written version and the brief details of the version are as follows :-
The R.O plant installed by the complainant is not supplied by the
opposite party and it is admitted that the opposite party entered in to
an agreement for annual maintenance and there is no fixed guarantee for
the quantity/quality of specifically treated out put water which depends
on the quality and condition of the membrane which is one of the
important parts in the R.O plant and the quality of out put depends upon
the quality of input water when the flow is reduced membrane has to be
cleaned with some special chemical and accordingly the opposite party
carried out the maintenance of the R.O. Plant and pressure tube supplied
by the opposite party as given life up to April 2007 and it was replaced
in May 2007 which is working in good condition only after cleaning was
made the flows of the water lever was increased in February 2007 which
was continued up to September 2007 due to technical and thorough
knowledge of the opposite party. As per the contract spares are to be
supplied by the complainant and in the month of August 2008 the
complainant was suggested for replacement of some critical spares in the
R.O. plant and other units. But the complainant did not change even a
single spare part and ordered. The opposite party to operate the plant
without change any spares. The opposite party is to maintain only up to
the out let of the R.O plan and pressure regarding the other parts like
boiler kitchen etc., The persons employed by the complainant are very
weak knowledge in their field and they have devoid from the standard
norms of operation. The complainant paid maintenance charges only up to
May 2008 at the rate of Rs.25,000/- p.m but the operators and engineers
of the opposite party worked in the plant till end of October 2008 and
from June 2008 to October 2008 complainant has not paid the maintenance
charges and spare parts value Rs.26,7235/- in all Rs.1,51,735/- and
thereby there was no deficiency of service on the part of the opposite
party complaint to be dismissed.
(3.) Both sides have filed their proof affidavits and documents of both
sides are marked as Exhibit A1 to A13 and Exhibit B1 to B5.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.