JUDGEMENT
M.THANIKACHALAM, J. -
(1.) The complainant claiming a total sum of Rs.94,30,215/-, has filed this
case under Section 17 of the Consumer Protection Act, on the following
grounds:-
The complainant had insured the stock and the mill premises with the
opposite parties, under two policies, viz (i) Standard Fire & Special
Perils Policy No.F/220/2001, dated 26.06.2000 for a sum insured to the
tune of Rs.8,01,000/- and Rs.30,00,000/- for the Building of Cotton Yarn
Godown and Stock and Stock in process in the Cotton Yarn Godown
respectively and (ii) Standard Fire & Special Perils Policy
NO.414102/24000/F/636/2001 dated 25.01.2001 for a sum of Rs.50,00,000/-
covering the Stock in Godown-Stock of cotton in bales and borahs. On
5/6.05.2001 at about 1 a.m. there was a fire causing extensive damages
and loss to the complainant?s godown and stocks, which they have stored
the cotton, procuring for production, expecting power improvement also.
Immediately after the fire, the same was informed to Sayalkudi Fire
Station, Perunali Police Station by wireless. Distance between Sayalkudi
and Perunali is about 20 kms and therefore, fire tenderer arrived only by
about 2.45 a.m., in addition to other fire tenders from Kamuthi and
Muthukalathur. Despite their effort to douse the fire, the entire stock
of the cotton stored in the cotton godown caught fire and entirely
devastated, for which, FIR was also registered at Perunali Police
Station, further informing the matter to the Insurance Company, forthwith.
(2.) The third opposite party arranged for a surveyor, who conducted
survey, investigated the matter initially, then jointly along with
M/s.Wilton & Co. from Chennai. As requested by the Surveyors, then and
there, all the necessary documents were submitted to them, thereafter on
10.06.2001, the claim was lodged for Rs.84,30,215/- but there was no
honest efforts taken, by the opposite parties to settle the claim and the
hope of the complainant for early settlement shattered.
(3.) The opposite parties instead of settling the claim of the complainant,
to the shock and surprise, appointed a second surveyor, who had visited
the Mill premises, once again requested the documents and other details,
which were already furnished to the first surveyor and despite that also,
the complainant submitted all the records, required. There was no
occasion for the opposite parties, to appoint a second surveyor, that
too, after 18 months of the date of incident, namely fire accident. From
September 2002, there was not even a whisper from the second surveyor,
thereby compelled the complainant to write number of letters, causing
mental agony, not only to the Surveyor, but also to the opposite parties.
Finally on 10.03.2003, the complainant received a letter informing that
the claim was repudiated and the grounds stated therein are all
frivolous, unsustainable. It is not the case of the opposite parties
also, that the fire was engineered by the complainant, whereas it is the
specific finding of the surveyors, that the fire was accidental, when
that is the case, the repudiation of the claim invoking Clause 6 (b) and
8 of the Fire Policy is most unwarranted, invented only to evade the
liability, denying the legitimate claim of the complainant, that should
be construed as gross negligence and deficiency in service. On account of
the non-settlement of the claim, which is quantified at Rs.84,30,215/-,
the complainant was put to mental agony, for which, the complainant is
entitled to a sum of Rs.10 lakhs as compensation. Thus, alleging
negligence and deficiency, this consumer complaint was lodged for the
total recovery sum of Rs.94,30,215/-.;