JUDGEMENT
GYAN SUDHA MISHRA, J. -
(1.) THIS is an application for appointment of an Arbitrator under Section 11(6) read with Section 11 (8) of the Arbitration and Conciliation Act, 1996 on the averment that the applicant M/s Nagarjuna
Construction Company Ltd. had been awarded a contract in response to a tender invited by the
State of Jharkhand to execute, inter alia, the work of construction of Earthen Dam, Ogee Chute
Profile Spillway, Right Main Canal, Left Main Canal, Approach Channel, Spill Channel, Canal Drop,
Cross Drainage Work, SLR Bridge, Water Escape, Inlet, Distribution Network to irrigate 90 per cent,
of command area etc. and the Petitioner participated in the tender process and was ultimately
granted the aforesaid tender for executing construction work of earthen Dam and ancillary work
known as 'Suru Reservoir Project'. The Order dated 14th August, 2004 to that effect
was issued by the Joint Secretary, Water Resource Department, Government of Jharkhand and in
view of this, an agreement was executed between the applicant and the Respondent -State of
Jharkhand, wherein Clause -23 had been incorporated. This Clause 23 envisages that in case any
dispute or difference arises between the parties or either of them upon any question relating to the
meaning of the specifications, designs, drawings and instructions or as to the quality of
workmanship or materials used on the work or as to the construction of any of the conditions or
any clause or thing therein contained or as to any question, claim, rights of the parties or any
matters or things whatsoever in any way arising out of or relating to the contract designs, drawings
specifications, estimates, instruction Order or these conditions or otherwise concerning the work or
the execution or failure to execute the same whether arising during the progress of the work or
after the completion or abandonment thereof or as to the breach of this contract, then either party
shall forthwith give to the other notice of such dispute or difference in writing and such dispute or
difference shall be referred to the Engineer in Charge. The E/l will take decision within 30 days.
Even if the matter is not resolved it will be referred to the Chief Engineer/Engineer in Chief where it
will be resolved in 45 days. The Clause further indicates that if the party is not satisfied with the
decision, then the matter may be referred for arbitration on such request as per Rule under the
Arbitration & Reconciliation Act, 1996.
(2.) THE applicant has summed up its case by stating that it had started the work in 2004 and 80 per cent of the work has already been executed by the applicant on the available area. It has also
been admitted that the Appellant has been paid a sum of rupees twenty three lakhs as against its
claim of rupees three Crores payable by the Respondent -State for the work already executed but,
the same has not been accepted or admitted by the Respondent -State.
Hence, a dispute arose in regard to the balance payment over and above rupees twenty three lakhs which has been claimed by the applicant from the Respondent - State. The applicant,
therefore, has come up with a case that the due payment which was claimed by the applicant has
not been paid and, therefore, a dispute emerged which was raised before the Engineer -in -Chief as
per Clause -23 of the Agreement. It was stated that the Engineer -in -Chief did not resolve the
dispute and the Respondent -State which had entered into an agreement with the applicant also
did not refer the matter to the Arbitrator for adjudication of the dispute despite its provision in the
agreement.
(3.) FROM the aforesaid facts, it is clear that a dispute between the parties has prima facie arisen bonafide and it is also an admitted position that Clause 23 has been incorporated in the
Agreement specifically indicating that the matter shall be referred to the Arbitrator in the event a
dispute arises between the contracting parties.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.