JUDGEMENT
D.G.R.PATNAIK, J. -
(1.) Challenge in this appeal is against the order of the learned
single Judge passed in W.P(C) No. 746 of
2008, whereby the writ application was
disposed of with certain observations directing
the respondents to raise a provisional bill
and after considering and deciding upon
objection, if any, by the petitioner, to
prepare and raise the final bill under Section
126 of the Electricity Act and, with a
further direction to restore electrical
connection to the petitioner's factory premises
subject to the petitioner's depositing a sum of
Rs. 3.00 crores. The amount so deposited
was made subject to final decision that may
be taken by the respondents after
considering the objections filed by the petitioner
against the provisional bill.
(2.) Prayer in the writ application as made
by the appellant/petitioner was for
directions to the respondents :
1]. To forthwith restore the power supply
of the petitioner, which was disconnected
by the respondent No. 5/7 on 1-2-2008.
2]. To not to take any coercive/penal
action against the petitioner pursuant to the
F.I.R. lodged against the petitioner.
3]. To direct the respondents not to raise/
charge any average/guarantee bill upon the
petitioner for the disconnection period.
4]. To award adequate compensation/cost
to the petitioner for the purported illegal
actions of the respondents.
(3.) Brief facts of the case is that the
appellant/petitioner had taken electricity
connection from the respondent Damodar
Valley Corporation (DVC) (hereinafter referred
to as the 'Corporation') for its factory at
village Chaha in the district of Ramgarh in the
year 2000. The supply of electricity was
made through the appellant's own erected
supply lines. Initially, the appellant was the
only consumer and therefore, single meter
was installed by the supplier at its own end.
There was no separate meter installed in the
premises of the appellant. On account of the
considerable distance from the sub-station
to its factory premises, the appellant had
suffered huge amount of transmission loss
to the extent of Rs. 5.00 crores in between
January, 2001 to October, 2004 to which,
though respondent supplier had agreed to
reimburse the appellant, but later, did not
pay any heed in the matter. The appellant
filed a writ application vide W.P. (C) No. 6023
of 2001 before this Court and obtained a
direction from the Court vide order dated
29-1-2002 against the DVC authorities to
take a final decision in the matter of grant
of transmission loss to the appellant within
30 days from the date of receipt of the
Court's order after giving reasonable
opportunity of hearing to the appellant. A further
direction was contained in the Court's
order to the respondents to revise all the bills
and to refund/adjust the excess paid
amount. The respondent DVC failed to comply
with the aforesaid order of the Court as
a result of which, a sum of Rs. 5.00 crores
as claimed by the appellant as excess
amount paid by them, remained pending
with the respondents. The respondent DVC
authorities continued to raise the bills upon
the appellant on the basis of the meter,
which was installed in the sub-station till
October, 2004, whereafter a separate meter
was installed within the premises of the
appellant. The bills for electric consumption
began thereafter to be raised on the basis of
the readings in the meter installed within
the premises of the appellant and till
December, 2007 appellant had continued to
pay all the monthly bills., However, despite
the fact that the feeder line was installed by
the appellant at its own post, the
respondent DVC chose to supply electrical energy
to two other consumers by the same feeder
in July, 2006 and in March, 2007 through
only single meter installed at the
sub-station of the DVC, although separate meters
were installed in the individual units of the
consumers. The appellant claims that
under the terms of the agreement, for the
supply of electric energy, it is the supplier who
has to install the metering equipment and
to maintain them. Such meters are supposed
to be properly sealed and the seals are not
to be interfered with by the consumers, or
even by the supplier except in the presence
of their respective duly authorized representatives.
The grievance of the appellant is that on
1-2-2008 the respondents 6, 7 and 8
visited the appellant's factory premises on the
plea that they had come for maintenance
work of the metering units and thereafter,
disconnected the power supply without
giving any opportunity to the appellant and
despite protest made by the appellant's men
who were present. The disconnection was
carried out by breaking open the seals of
the meter room, meter boxes and junction
box. It is alleged that when the appellant's
men had wanted to resist, the respondent
Executive Engineer had even invited the
police to thwart the resistance. It was on
the next day, that the appellant received
message telephonically followed by FAX
message from the respondent No. 8 that electric
supply was disconnected under superior
orders and on the ground that the electric
supply cable was found punctured at
several points by some illegal methods and the
electrical energy was pilfered by artificial
means leading thereby to a wide variation
to the extent of 80% in the meter reading
recorded at the premises of the appellant.
The appellant was also informed that the
respondent No. 7 had lodged an FIR against
the appellant on the allegation of theft of
electrical energy. Claiming that there could
not be any possibility of pilfering or stealing
energy through pin-holes from the 33 KV
load of electric supply cable and further
claiming that the allegations in the FIR are
totally false, concocted and misleading, the
appellant had challenged the very authority
of the respondents either to enter into the
factory premises of the appellant for any
search or seizure or even to lodge FIR against
the appellant under Section 135 of the
Electricity Act. The appellant also challenged the
authority and jurisdiction of the respondent
Nos. 5 and 7 or any of the respondents to
disconnect the power supply of the
appellant. The appellant has claimed that though,
under Section 135(1-A) of the Electricity Act,
licensee or supplier may disconnect the
electric supply in the event of detection of theft
of electricity, but power to enter into the
premises and to make inspection, search
and to break up seals etc., is vested only
with any officer of the licensee or supplier
who is authorized in this behalf by the State
Government and further, the disconnection
of the electric supply can be made only by
the Appropriate Commission or any officer
of the licensee or supplier who is duly
authorized and not by the respondents. It is
further claimed that only such officer who
is duly authorized, has the power to lodge
complaint in writing relating to commission
of offence, in the police station, and such
power being not vested with the respondent
No. 7, the entire acts and deeds of the
respondents is totally illegal and the
prosecution of the appellant under Section 135 of
the Electricity Act is therefore, illegal and
against the provisions of law.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.