M/S. SHANKAR FERRO ALLOYS PVT. LTD. Vs. JHARKHAND URJA VIKAS NIGAM LIMITED
LAWS(JHAR)-2017-11-189
HIGH COURT OF JHARKHAND
Decided on November 17,2017

M/S. Shankar Ferro Alloys Pvt. Ltd. Appellant
VERSUS
Jharkhand Urja Vikas Nigam Limited Respondents

JUDGEMENT

SHREE CHANDRASHEKHAR,J. - (1.) Petitioner's grievance is that on 25.09.2017 the electricity supply at its premises has been illegally disconnected and on an allegation of theft of electricity First Information Report vide Chakulia P.S. Case No. 29 of 2017 has been lodged for the offence under sections 379, 420 and 427 I.P.C and sections 135/137/138 of Indian Electricity Act, 2003.
(2.) Briefly stated, the petitioner-M/s Shanker Ferro Alloys Pvt. Ltd. was granted HTSS connection with sanctioned contract load of 2000 KVA and the connection was energized on 15.12.2006. On 26.05.2017, a new metering unit was installed at the petitioner's premises. When the respondents' officials visited the petitioner's premises on 25.09.2017 they allegedly found CT wire of "Y" phase to check-metering unit severed and pinhole in CT wire of 'R' and 'B' phase punctured. Inside the metering room, it is alleged welding over metallic sheet and paper seal both were found damaged. On these allegations, a First Information Report was lodged on 26.09.2017. A provisional assessment dated 27.09.2017 under second proviso to Section 135 (1-A) of Electricity Act, 2003 read with Clause 11.9 of the Electricity Supply Code Regulations was served upon the petitioner.
(3.) Sri Sunil Kumar, the learned Senior counsel for the petitioner submits that leaving aside merits of the matter, apparently provisional assessment dated 27.09.2017 is illegal, inasmuch as, the alleged period of theft has been counted from 26.05.2017 to 26.09.2017, whereas the respondents' own document would disclose that meter reading at the petitioner's premises was taken on 04.09.2017, and on that day nothing wrong or unusual was found. It is further contended that dehorse the method of calculation for provisional assessment under the Electricity Supply Code Regulations, 2015, the respondent-Nigam has multiplied the total unit of alleged theft by 2. In the above facts, contention raised on behalf of the petitioner is that the mandate under section 43 of the Electricity Act, 2003 is sought to be frustrated by issuing arbitrary assessment order. The learned Senior counsel refers to the order passed in M/s Gajanan Ferro Pvt. Ltd. v. Jharkhand Urja Vikash Nigam Limited in W.P.(C) No. 4097 of 2017 .;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.