JUDGEMENT
-
(1.) In this application under Section 11 (6) of the Arbitration and
Conciliation Act, 1996 petitioner has prayed for appointment of Arbitrator for settlement of
dispute and claim of the petitioner for the
work undertaken in the District of Godda
for construction of rural road including
bridge and culverts etc.
(2.) Petitioner's case is that after completion of the formalities as required under the
advertisement, a contract agreement was executed and signed on 19-3-1997 between the
parties for the construction of rural road
including bridge and culverts in Boarijore
Block of Godda. After execution of the agreement petitioner said to have
utilized all adequate resources as such manpower, plant
and equipment and necessary infrastructure
to ensure that the work was continued in
full swing so as to complete the entire work
within the fixed time. It is contended that
the sites of the work were handed over to
the petitioner on 12-5-1997 and the work
was commenced on 24-5-1997. However, the
work was badly obstructed to the reasons
and circumstances beyond the control of the
petitioner. According to the petitioner,
Clause 34 of the award of the contract
speaks about the appointment of adjudicator. Petitioner's case is that claim was made
on 18-5-2002 before the retired Engineer-
in-Chief, Technical Vigilance Cell, Road Construction Department, Govt. of Bihar but
nothing was done. Petitioner alleged to have
requested the respondent for appointment
of Committee of Arbitrator in matter of disputes arising out of contract package No.
49, construction of rural road including
bridge and culverts by sending representation dated 29-10-2002. Petitioner said to
have again made representation on 31-3-
2003 and 4-8-2004 but all in vein. Hence,
this application.
(3.) A counter affidavit has been filed by
the respondents stating inter alia that application under Section 11 (6) of the Act is
wholly misconceived and is not maintainable. It is stated that terms of agreement
does not sanction appointment of Arbitrator rather according to the agreement, matter
can at best be referred to the adjudicator. Respondent's further case is that the
instant application is hopelessly barred by
limitation and even the matter cannot now
be referred to the adjudicator. Respondents'
case is that petitioner did not complete the
work within 24 months from handing over
the site. The date of completion of work was
23-5-99. Respondents' further case is that
petitioner for the first time made his claim
on 18-5-2002 when the project was closed
as far back as in June, 2000.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.