DAYAL STEELS LTD. AND ORS. Vs. JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AND ORS.
LAWS(JHAR)-2015-2-157
HIGH COURT OF JHARKHAND
Decided on February 19,2015

Dayal Steels Ltd. And Ors. Appellant
VERSUS
Jharkhand State Electricity Regulatory Commission And Ors. Respondents

JUDGEMENT

Prashant Kumar, J. - (1.) IN the aforesaid two writ applications, common question of facts and law arose, therefore, are heard together and disposed of by this common order.
(2.) IT appears that respondents Damodar Valley Corporation (hereinafter referred to as 'DVC') raised a bill of Rs. 2.66 Crore on 06. 06. 2008 (Annexure -S.A. -1) for the period commencing from 01.05.2008 to 16.05.2008 on average basis. The aforesaid bill challenged by the petitioner vide WPC No. 3277 of 2008, on the ground that no notice given to the petitioner before declaring that the meter, installed in the premises of petitioner, has become defective. The petitioner further challenged the bill on the ground that the same has not been raised according to the provision of Clause 11.3 of the Electricity Supply Code 2005 (hereinafter referred to as the 'Code'), which provides that in case of defective meter, the bill can be raised on the basis of average consumption of last 12 months immediately preceding the month in which the meter was last read. It is further contended that it is imperative for the respondent to send the meter for testing before a third party agency nominated by Jharkhand State Electricity Regulatory Commission (hereinafter referred to as JSERC). It appears that during the pendency of aforesaid writ application, petitioner paid Rs. 1.8 crore to the respondent towards the bill amount. It is worth mentioning that aforesaid writ application disposed of by a bench of this Court vide order dated 22.08.2008 (Annexure -3) whereby and whereunder respondents were directed to send the meter to any of the three agencies, notified by the JSERC, with prior intimation to the petitioner. It is further ordered that if petitioner so desire, may remain present before the agency, at the time of testing of the meter. It appears that in pursuance of the aforesaid order, respondents sent the meter to M/s. National Physical laboratory, New Delhi for necessary testing. It is also not out of place to mention here that the respondents gave prior intimation to the petitioner as directed by this Court. It then appears that the National Physical Laboratory, New Delhi after testing the meter concluded vide Annexure -7/1 that the meter was not functioning correctly. Thus, according to it the meter was defective. Thereafter respondents vide order dated 03.06.2010 intimated this petitioner that since the meter was found defective, therefore, the earlier bill raised on 16.6.2008 was correct. Hence, petitioner pay rest of the amount. This letter is impugned in WPC No. 3650 of 2010.
(3.) THE petitioner has challenged another four bills in WPC No. 5102 of 2008, issued on 09.09.2008, 03.10.2008, 03.11.2008 and 04.12.2008, which relates for the following periods i.e. 02.08.2008 to 31.8.2008, 01.09.2008 to 30.09.2008, 01.10.2008 to 31.10.2008 and 01.11.2008 to 30.11.2008 respectively. These bills also challenged on the ground that the same were issued in contravention of provision contained in Clause 11.3 of the Code.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.