JUDGEMENT
-
(1.) In this application under
Section 11(6) of the Arbitration &
Conciliation Act, the petitioner has prayed for
appointment of an independent arbitrator
and for reference of the dispute arose
between the parties to the said arbitrator
for adjudication.
(2.) The petitioner was awarded the work
of construction of JRD Tata Technical
Training Institute at Gopalpur. District
Ganjam, Orissa vide work order dated
10.12.1996. The contract work was valued
at Rs.4.48 crores, but as per the drawings
issued the total contract work on accepted
rates was about Rs. six crores. The
petitioner's case is that in course of work,
the scope of work was revised drastically and
as such the petitioner raised claim of
Rs.96.35 lakhs, but the claim of the
petitioner was not settled. It is contended
that the respondents have made part
payment and in spite of notice, failed to pay
the entire amount. The petitioner, thereafter,
sent notice dated 15.11.2002 to the
respondent demanding Rs.197.11 lakhs
along with 18% interest. Thereafter, the
petitioner sent another notice dated
17.12.2002 invoking the arbitration clause.
It is alleged that the respondent failed to
agree with the single arbitrator nominated
by the petitioner and consequently the
present application was filed.
(3.) The respondent - Tata Iron & Steel Co.
Ltd. filed counter affidavit stating that the
petitioners have resorted to arbitration clause
No. (14.2) without first resorting to clause 14.1
which is condition precedent before resprting
to the arbitration clause. The respondent's
further case is that one M.N. Dastur & co. Ltd.
was a Consulting Engineer of the said Project.
The petitioner had written a letter on 8.3.2001
to the said Consulting Engineer including the
final bill for the said work. The Consulting
Engineer passed the bill after statutory and other
deductions. The petitioner, however, did not
submit 'No Claim Certificate' despite repeated
reminders. However, the petitioner approached
the respondent and everything was settled. The
respondent's further case is that as a matter of
fact, by letter dated 20th October, 2001, the
petitioner gave 'No Claim Certificate' stating that
the petitioner does not have any further claim.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.