JUDGEMENT
M.Y.EQBAL, J. -
(1.) HEARD Mr. Rajiv Ranjan, learned counsel for the petitioner and Mr. R.K. Singh learned counsel for the respondents.
(2.) IN this application filed under Sec.11(6) of the Arbitration and Conciliation Act, 1996, the petitioner has prayed for appointment of independent Arbitrator for settlement of dispute and
claims of the petitioner for the work relating to and in connection with construction of temporary
Houses at Govindpur Project of Kathara Area of the respondents.
Petitioner 'scase is that by virtue of work order No. GM/960/Temp/Houses/Govindpur/KTA/95/230 -32 dated 17.1.1996 respondents awarded work of
construction of temporary houses at Govindpur Project at Kathara Area to the claimant. It is
alleged that the site was partly made available to the claimant which was completed within a short
time but some of the site was made available after lapse of completion period. Petitioner alleged to
have made several attempt to start the work but the villagers could not allowed to complete the
work. Thereafter, several correspondences were made in relation to completion of work, as a result
of which petitioner alleged to have sustained loss of Rs. 67,61,975.00 on several counts. The
petitioner/claimant vide letter dated 24.9.2004 nominated their Arbitrator and requested the
respondents to refer the matter to the Arbitrator in terms of Clause 9.7.5 of the General Terms and
Conditions but the respondents could reply and could not appoint their Arbitrator.
(3.) RESPONDENTS in their Counter affidavit have stated that in compliance of mandatory requirement of law and the scheme framed by the Court, petitioner has not filed original agreement or duly
attested copy thereof. The general terms and Conditions as contained in Annexure -2 to the
application is not the part of the contract entered into by the petitioner. Clause 9.7.5 referred by
the applicant is not the arbitration clause.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.