JUDGEMENT
N.N.TIWARI, J. -
(1.) IN this writ application, the petitioner has prayed for quashing the order issued by the Notification bearing No. 11, dated 29.1.1998, under the signature of the Deputy Secretary to the Government,
State of Bihar whereby the petitioner has been awarded two fold punishment (i) for recovery of Rs.
1,94,580.00 with a rider that if it is not recovered during the service tenure, it may be recorded even from the retiral dues; and (ii) bar on promotion for two years.
(2.) THE petitioner 'scase is that in the year 1984 -85 an agreement L.C.B. 7 of 1984 -85 was entered into between the authorities of respondent No. 3 and one Budhu Construction Pvt. Ltd.
for earth work and bed lining between 7.22 to 22.49 and 25.25 to 29.83 R.D. of Kharkai Barrage,
Right Main Canal. The said work was executed by the contractor and the whole amount of
provisional sanctioned rate was disbursed to the contractor by the order of Chief Engineer,
communicated by letter No. 1615, dated 26.11.1988. At that time, one Ajit Prasad and thereafter
Shiv Raj Singh were the Executive Engineers. By letter dated 19.9.1988 and 3.12.1988, the then
Executive Engineer requested the Superintending Engineer for payment of work done as extra -
item in the shape of rock cutting and blasting worth about Rs. 36.55 lakh. Petitioner 'scase is
that he joined, subsequently, on 31.12.1988. According to the petitioner, even the said
recommendation of the then Executive Engineer was considered by a Tender Committee under the
chairmanship of M.C. Subarna, Administrator of the Project and other members including all Chief
Engineers and the said committee had approved the payment of the said amount for the extra -item
of work. According to the petitioner, he was not at all connected with the said work at the time of
its allotment, execution or recommendation of payment for extra work. However, after payment was
made for the said extra work, some controversy arose which led to an inquiry and in the said
enquiry, it was concluded that the payment was contrary to the terms of the agreement and
departmental rules. The State Government then decided to hold departmental inquiry against 24
officers including the petitioner. The petitioner was served with a letter No. 3041, dated 1.12.1990
asking to explain the allegations against him. The petitioner submitted his explanation by his letter
No. 1294, dated 22.12.1990 denying the allegations made against him. Thereafter a charge -sheet
following by Memo No. 1244, dated 23.5.1991 containing articles of charges and appointing an
inquiry officer. The petitioner submitted his reply dated 19.6.1991. Again, another charge -sheet
was issued after termination of the enquiry officer BN. Thakur containing the similar articles of
charges and the petitioner submitted his reply on 1.9.1993. The said charge -sheets and replies
have been made Annexures 4, 4/A, 5, 5/A, 6 and 6/A respectively. The Enquiry Officer completed
his enquiry against A.K. Srivastava, Superintending Engineer and also the then In -charge Chief
Engineer and member of the Tender Committee, which approved payment for extra work with his
recommendations for exonerating them of the charges. However, the petitioner was awarded
punishment on the same charges by order dated 31.5.1995. The petitioner preferred writ
application against the said punishment order being C.W.JC. No. 12235 of 1995 in the Patna High
Court and by order dated 31.5.1995 passed therein, the punishment order was quashed holding
that the punishment was imposed without furnishing a copy of the inquiry report of the flying
squad, which was relied upon by the disciplinary authority for imposing punishment. The
respondents were, however, directed to furnish a copy of the said report giving liberty to the
petitioner to file his reply and thereafter directed the respondent authorities to pass a fresh
reasoned order in accordance with law. According to the petitioner, thereafter, he approached the
authorities concerned, but neither the report of the flying squad was handed over to him nor the
same was shown to the petitioner and again the impugned order dated 29.1.1988 has been
arbitrarily passed awarding two fold punishments as first above mentioned.
A counter -affidavit has been filed on behalf of the State -respondents, wherein it has been stated that the petitioner 'sservice record is tainted and blemished; he has been inflicted
punishments for different types of omissions and commissions committed by him during his service
tenure. It has been stated that while the petitioner was posted as Executive Engineer at Kharkai
Canal Division, Jamshedpur, Adityapur in the year, 1988 -92, he had made irregular payment of Rs.
12.58 lakh to the contractor, M/s. Bhandari Construction. The said irregularities were detected and in accordance with Rule 52 -A of the Civil Services Classification (Control and Appeal) Rules, a
proceeding was initiated against him. Charge -sheet was served, but the petitioner did not submit
his explanation. The Government, then, examined the allegations and on the basis of the
documents related to it and available on record, the charges of excess payment were found
proved against the petitioner and on that basis the punishment was inflicted by the impugned
letter dated 29.1.1998 (An -nexure -1). The respondents have, thus, prayed that the
petitioner 'sClaim is wholly unfounded and the writ application is fit to be dismissed.
(3.) MR . B.P. Pandey, learned Senior Counsel appearing on behalf of the petitioner submitted that Annexure -1, the order of punishment issued against the petitioner is cryptic, non - speaking, based
on no reasons and the same is violative of the provisions of law as well as the clear direction
given to the respondents by order dated 1.10.1996 in C.W.J.C. No. 12235 of 1995. Learned
Counsel submitted that the order has been passed stating that the irregularities were scrutinized at
the departmental level and it has been concluded that the petitioner had deliberately caused
financial loss to the Government and has committed irregularity and misappropriation of the
Government fund. But there is no discussion of evidence and material on record and no reason
has been recorded for coming to the said conclusion. The impugned order is thus whimsical,
perverse and illegal and is liable to be quashed.;