JUDGEMENT
NARENDRA NATH TIWARI, J. -
(1.) THE petitioner in this writ application has prayed for quashing the order No. 118, dated 22.5.2005 contained in Annexure 8 whereby decision has been taken to realize Rs. 3,97,773 from the petitioner who is a retired Junior Engineer of the Road Construction Department. The said
decision has been taken in a proceeding initiated against the petitioner under the provisions of
Rule 43 (b) of the Bihar Pension Rules. The short facts of the case is as follows :
(2.) THE petitioner was appointed as a Civil Overseer in the year 1981. He was made a permanent Junior Engineer in the year 1985. The petitioner was transferred to Swarnrekha Road Construction
Division, Ghatshila as junior Engineer where he had joined on 11.12.1987. The Division of
Swarnrekha Road Command Area, Road Construction Department, Ghatshila was reconstituted
and transferred to Road Division, Lohardaga. The petitioner then was transferred to Lohardaga
wherefrom he retired on 31.01.2002 on attaining the age of superannuation. On reconstitution of
Swarnrekha Road Command Area, Ghatshila, the Executive Engineer, Lohardaga by his letter No.
66, dated 16.6.2001 directed the petitioner to hand over charge of records, materials etc. to the Executive Engineer, Swarnrekha Command Area, Road Division, Jamshedpur. The petitioner,
thereafter, prepared the charge report of Ghatsila Hulung Road and submitted the same to Sunil
Kumar, Junior Engineer on 21.8.2001 and requested him to take over the charge. The Executive
Engineer, Jamshedpur one Bijay Kumar Mishra was also requested for the same, but because of
the non -cooperation of said Sunil Kumar and Bijay Kumar Mishra, the petitioner could not hand
over the charge. According to the petitioner, he had made several requests in that regard to the
concerned authorities but to no effect. The petitioner, thereafter, retired and after retirement he had
to prefer a writ application being W.P. (S) No. 2825 of 2002 seeking an order of this Court to direct
the respondents to arrange for taking over of complete charge of Ghatshila Hulung Road from the
petitioner as he has already retired from service. The petitioner had also prayed for a direction for
payment of amount of gratuity which was withheld on the ground of holding the charge of
Ghatshila Hulung Road by the petitioner. An interim order, dated 13.7.2002 was passed in the said
writ petition whereby the Secretary, Road Construction Department was directed to ensure
handing over and taking over of the charge as prayed for by the petitioner. Ultimately, after the
said order, the charge was handed over on 5.8.2002. The respondents, thereafter, filed a counter
affidavit mentioning therein that during the handing over of charge, shortage of materials worth Rs.
,97,643/ - was found. The said writ petition was disposed of with an observation that a proceeding under Rule 43 (b) of the Bihar Pension Rules may be initiated for the alleged shortage
of materials and that the 75% of the gratuity amount be paid to the petitioner withholding 25% of
the amount in contemplation of the said proceeding under Rule 43 (b). The department, thereafter,
initiated a proceeding under Rule 43 (b) of the Bihar Pension Rules against the petitioner alleging
that irregularities were committed by the petitioner during his posting as Junior Engineer,
Swarnrekha Command Road Division, Road Construction Department, Jamshedpur and that the
petitioner allegedly embezzled the articles worth Rs. 6,97,643/ - which were found short when he
handed over the charge of the store. The petitioner filed his reply denying the charges. Thereafter,
the enquiry was conducted and on completion of the enquiry, enquiry report was submitted
(Annexure 5). The enquiry officer, inter alia, found that the handing over and taking over of charge
was made on the basis of conjecture without any accurate measurement and that physical
verification of the articles after such a long time was not possible. It was further found that six
number of home pipes were never handed over to the petitioner. It was also observed that had
the handing over and taking over of charge taken place in time, such situation would not have
arisen. On the basis of the said enquiry report, the impugned order has been passed whereby a
decision has been taken to realize Rs. 3,97.773/ - from the petitioner.
3 A counter affidavit has been filed on behalf of the respondents wherein it has been stated that despite several directions by the Superior Officers, the petitioner did not hand over the charge and
only after the order was passed in W.P. (S) No. 2825 of 2002 on 06.5.2002, the petitioner handed
over the charge to the concerned authority, that too after he retired from the services and in the
said process a shortage of materials worth Rs. 3,97,773/ - was reported and it was due to lapses
on the part of the petitioner. It has been further stated that the facts and circumstances of the case
were duly considered during the departmental proceeding and the officers other than the petitioner
were asked explanation and on that basis they have also been penalized. The name of the
officers is mentioned as Sunil Kumar, Junior Engineer and Bijay Kumar Mishra, Junior Engineer.
The memo by which they were penalized have also been enclosed as Annexure II.
(3.) FROM perusal of the enquiry report, the contention of the petitioner is corroborated. It has been found in course of the enquiry that the persons other than the petitioner were also responsible for
not completing the said process of handing over and taking over of charge, the amount of loss
determined has no basis and the same has been arbitrarily assessed on mere conjectures as no
measurement of the articles were taken while handing over and taking over the charge of the
stores, physical verification has not been made as it has been said that it was not practically
possible. It has been further found that six hume pipes which were also included in assessing the
loss were not given in the charge of the petitioner and actually the price of the articles ruling on the
day when the charge was handed over to the petitioner, has been taken into consideration as the
basis of assessment of loss. It has not been specifically found by the enquiry officer that for the
alleged loss the petitioner was held guilty or that he has embezzeled the said amount as has been
alleged. A letter written by the then Executive Engineer, Road Construction Department. Road
Division, Lohardaga to the Government, which is on record, clearly goes to show that in fact the
petitioner had been making requests to the concerned person Sunil Kumar and also to the
Department time and again but the charge was not taken over by said Sunil Kumar. The executive
engineer in the said letters has clearly mentioned that Sunil Kumar by letter dated 17.9.2001 had
demanded Rs. 25.000.00 for expenses for making necessary arrangement for taking over the
charge and for keeping the process in" abeyance till the said fund is released. The respondents
have not made categorical statement denying the said letter, on record. No specific stand has
been made in the counter affidavit except the bald repetition of the statement that the petitioner
was at fault. The alleged fault of the petitioner, however, could not be substantiated by any
material or any evidence on record.;