JUDGEMENT
P.K.BALASUBRAMANYAN, J. -
(1.) THIS appeal is by the plaintiff in a suit for recovery of the damages for breach of contract of supply of fire clay bricks and recuperator tubes by the first defendant company. The plaintiff invited
quotations for the supply of the above articles and the quotation of the first defendant was
accepted and on 8.1.1971, the plaintiff placed an order with the first defendant for supply of 14,
420.27 M.T. of fire clay bricks. On 3.2.1971 the plaintiff placed another order with the first defendant for supply of 31,917 pieces of recuperator tubes. The first defendant was to make
available samples for testing by the plaintiff. The supply was to commence after the samples were
approved. On 8.4.1971, the first defendant requested the plaintiff to arrange for an inspection of
fifty pieces of samples of recuperator tubes. Some samples were produced. The plaintiff tested
them and found that the recuperator tubes did not conform to the required drawings as per which
the supplies had to be made. The plaintiff called upon the first defendant to make available a fresh
supply of samples. The first defendant assured the plaintiff that fresh samples would be supplied.
After reminders were sent by the plaintiff, the defendant produced 18 pieces of bricks as sample
for Inspection by the plaintiff. The plaintiff found the sample defective and on 7/12th, October,
1971 called upon the first defendant to rectify the defects noticed in the samples and then to go ahead with a bulk manufacture for supply. According to the plaintiff, reminders were also sent to
the first defendant. On 23.2.1972, the first defendant promised to commence manufacture in lots
after two or three weeks. The Works Manger of the first defendant called on the Chief of Materials
of the plaintiff in the fourth week of May, 1972 and promised to commence the supply of tubes and
bricks if and after the time was extended. The plaintiff extended the time to commence supply by
two months. On 14.9.1972, the officers of the plaintiff visited the worksite of the first defendant.
The first defendant intimated the plaintiff that on being satisfied with the samples the first
defendants would supply materials at 1500 to 2000 pieces per month. The plaintiff again found on
testing the samples that the tubes were defective. On 14.10.1972, the first defendant informed
that 300 pieces of recuperator tubes would be ready for inspection by 27/28th October. 1972. But
nothing further was heard from the first defendant. Ultimately, on 8.1.1973, the plaintiff made a
final request to the first defendant to supply the materials contracted for, within thirty days and
informed the first defendant that on failure of thefirst defendant to do so. the plaintiff would be
constrained to procure the materials from other sources at the risk and cost of the defendants.
Since the first defendant failed to supply the materials, the plaintiff was constrained to purchase
materials from elsewhere at higher prices. On 4.2.1976, the plaintiff filed the suit for recovery of the
difference in prices as damages.
(2.) THE first defendant alone resisted the suit. The others did not contest. It raised a contention that the suit was barred by limitation. It further pleaded that the plaintiff had never approved the
samples and communicated the information to the first defendant and this resulted in the first
defendant not manufacturing and supplying the materials contracted for. The first defendant was
hence not liable for any damages. There was a strike in the factory of the first defendant and all
activities had to be suspended during the period of the strike. Hence, there was frustration of the
contract to supply the bricks and tubes contracted for. Since the performance of the contract
became impossible by frustration, the first defendant was not liable for damages for breach of
contract. The suit was liable to be dismissed.
The plaintiff examined a number of witnesses and proved the correspondence between the parties relating to the contract and the supply. The first defendant also led evidence. The other
defendants did not file written statement. The trial Court, on an appreciation of the pleadings and
the evidence in the case, held that the suit was in time. It also held that there was no frustration of
the contract which would enable the first defendant to get out of the obligation of paying the
difference in the market value at which it had agreed to supply the materials and at which the
plaintiff had to purchase it from others, on the failure of the first defendant to supply the goods
contracted for. It further held that the first defendant was guilty of breach of contract and hence
the plaintiff was entitled to claim the difference in market value as put forward by it in the plaint.
Thus, the trial Court decreed the suit. On appeal by the first defendant (sic) the trial Court holding
that the suit was barred by limitation and that the first defendant could rely on the doctrine of
frustration to get out of the liability for breach of the contract. But the learned Single Judge held
that there was a concluded contract between the plaintiff and the first defendant, overruling the
contention in that behalf raised by the first defendant. Thus, reversing the judgment and decree of
the trial Court, the learned Single Judge dismissed the suit. This dismissal is challenged by the
plaintiff in this appeal under Clause 10 of the Letters Patent.
(3.) BOTH the trial Court and the learned Single Judge have held that the contract for supply at the prices agreed upon, had come into existence between the plaintiff and the first defendant. The first
defendant was to supply samples, get them approved and thereafter was to commence supply.
The first defendant submitted samples, but the plaintiff informed the first defendant that the
samples were defective. On the third occasion, the first defendant agreed to make available
further samples after carrying out the rectification suggested by the plaintiff, but the same was not
done. The plaintiff repeatedly called upon the first defendant to get the samples approved arid to
commence the supply, but the first defendant failed either to make available the acceptable
samples or to get them approved. Then the plaintiff informed the first defendant that the plaintiff
was constrained to make purchases elsewhere at the risk and cost of the first defendant. It may be
noted that as per the terms of the contract, the time for supply could either be extended with
liability on the first defendant to pay penalty at 1 percent of the value going up to 10 percent
depending on the circumstances, or the plaintiff was entitled to recover the difference in the market
value between the prices at which the first defendant was to supply and the prices at which the
plaintiff had to purchase from outside. On the failure of the first defendant either to produce the
necessary samples as per the design and on failure to supply, it is obvious that the plaintiff was
justified in purchasing the materials from outside. There was no attempt made to contend that the
prices at which the first defendant was to make supply were unreasonable or the purchases by the
plaintiff were not at the prevailing market value. In this situation, it is obvious that the plaintiff was
entitled to recover the difference in prices from the first defendant on the failure of the first
defendant to perform its part of the contract. Thus, the trial Court, in our view, was fully correct in
upholding the claim of the plaintiff.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.