JUDGEMENT
-
(1.) LEARNED counsel appearing for the respondents submits that he has filed a counter affidavit on behalf of respondent No. 6 stating, inter alia, that
in pursuance of order dated 26.7.12 passed by SAR Court, the petitioner filed
an application on 12.1.2013 and for compliance of the order of the learned SAR
court, immediately one A.S.I., namely Simon Soy was deputed to stop the
construction work and accordingly the ASI along with police force went to the
spot at 3 P.M. and stopped the work and since then the status quo is being
maintained and no construction work is going on the said plot. It is further
submitted in paragraph 8 to the counter affidavit that for the same plot
previously a proceeding was initiated before S.D.M., Ranchi at the instance of
one Shekhar Lakra and others wherein, the petitioner, Pramod Lakra and others
were the second party in the said Misc. Case No. 1815/2012. It is further
stated that in para 2 of the Misc. Case it is alleged that the members of the
second party taking advantage of the situation, started the construction of wall
since 20.9.12 and, therefore, a proceeding was drawn under section 144 Cr.
P.C. on 29.9.12.
(2.) THE learned counsel for the petitioner submitted that the petitioner belongs to a Tribal Community and the land in question is also Tribal Land and
therefore it cannot be transferred to non tribal in view of the provision
contained in Section 46 of the CNT Act. However, an attempt has been made by
the land grabber to snatch the land of the Tribal by flouting the order of the
SAR Authority and the construction is carried out on the spot and therefore, an
enquiry is required to be conducted so as to ascertain the correct and present
position of the spot. It further appears that in SAR Case No. 122/2010-11, an
order dated 26.7.12 has been passed with regard to stoppage of work till the
final disposal of the proceeding and accordingly an intimation was sent to the
Lalpur Police Station. From perusal of the Counter affidavit, filed by respondent
No. 6 and more particularly, in view of averments made in paragraph-7, it
appears that immediately steps were taken by the police authorities and
accordingly the work has been stopped on the site as per order passed by the
SAR Authorities and at present, no construction work is going on.
The learned counsel for the petitioner pointed out that respondent No. 7 has committed fraud and obtained fraudulent decree by entering into a
compromise before the Competent Civil Court and the said proceeding has
been challenged by way of filing a Misc. Case No. 26/10, which is pending
before the learned Munsif, Ranchi. However, looking to the peculiar facts and
circumstances of the present case and more particularly, in view of the order
passed by the SAR Court, strict and proper compliance is also required to be
made by the authorities concerned. .
(3.) THE learned counsel for the petitioner while drawing attention to the averment made in para-7 to the counter affidavit, submitted that the work
has been stopped but the interference of respondent No. 7 and his persons is
still going on at the spot and they are creating disturbance and nuisance at the
spot and not allowing the present petitioner to visit the said spot. So far as this
allegation is concerned, the proceeding has been drawn under Section 144 Cr.
P.C. on 29.9.12 and the said proceeding is also going on and therefore, it would
be just and proper for this Court not to intervene with such proceeding but it is
expected by the authorities concerned to deal with and decide the proceeding
in accordance with law by giving reasonable opportunities of being heard to
the parties. Moreover, the concerned police authorities shall take necessary
steps in view of order passed by SAR court, so that the interest of the
petitioner, who belongs to a Tribal community can be protected and cannot be
allowed to affect adversely and the order passed by the competent court can be
complied with.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.