JUDGEMENT
M.Y.Eqbal, J. -
(1.) This appeal filed by the
defendant/appellant is directed against the
order dated 24.1.1997 passed by Sub-Judge
IV at Ranchi in money suit No. 11 of 1993
whereby he has allowed the prayer of the plaintiffs/respondents and
granted interim injunction restraining the defendant to proceed with
the notice and refer the dispute to the arbitration by appointing Arbitrator
(2.) It appears that plaintiff/respondent
M/s Builders Enterprises being the partnership
firm entered into a contract with the defendant/Union of
India for the purpose of undertaking construction work. Although plaintiff
commenced the construction work but because
of some reasons the contract could not be completed. Plaintiffs' case was that
because of default on the part of the defendant, the plaintiffs suffered huge loss to the extent of Rs
8,25,000/-. Consequently, the aforementioned suit was filed by
the plaintiff for a decree of Rs. 8,74,500/-
The defendant/ appellant contested the suit by filing written
statement stating inter alia that the suit is not maintainable inasmuch
as there is specific clause
namely, arbitration clause i e Clause 70 in the
Agreement which provides that all disputes
relating to the contract work is to be decided
by appointment of Arbitrator. The defendant
also denied and disputed the claim of the
plaintiffs.
(3.) During the pendency of the suit the
defendant filed a petition on 17.11.1994 praying to the Court to decide the issue of
maintainability of the suit as preliminary issue
It was contended that as per arbitration clause
contained in the agreement the suit is not
maintainable because all dispufes "are to be
decided by the Arbitrator. The learned Court
below after hearing the parties in terms of order
dated 23.1.1996 held that the suit is maintainable even if there is Arbitration clause in
the agreement. However, it was observed in
the said order that if the defendants are ready
to get the disputes settled as per Arbitration
clause they can take steps and serve notice to
the plaintiff. Consequent upon the aforesaid
order, defendant served a notice upon the plaintiff and invoked
the arbitration clause contained
in the agreement and sought to refer the matter to the Arbitrator named in the agreement.
On receipt of the notice plaintiff filed a petition on 18.4.1996 in the aforesaid suit and
made a prayer to restrain the defendant by an
order of interim injunction not to proceed with
the said notice and not to refer the matter to
the authority for arbitration. The Court below
by the impugned order allowed the application and restrained the defendant/appellant
from proceeding with the arbitration.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.