(1.) THE writ petition has been preferred by the Bokaro Steel Employees Co -operative, House Construction Society Ltd., Bokaro Steel City (for short Bokaro Co -operative Society) against the
letter No. 393 dated 21st February, 2003 issued by the General Manager (HRD), Steel Authority of
India Ltd. (for short SAIL), Bokaro Steel Plant, Bokaro, whereby and whereunder, the Honorary
Secretary of the Bokaro Co -operative Society has been informed of the outstanding dues accrued
and accumulated towards water charges in addition of amount of water charges for the month of
December 2002 and January, 2003.
(2.) THE grievance of petitioner is that the respondent while enhanced the rate of water charges illegally asked the petitioner to pay arrears of Rs. 1,33,94,066.33 ps.
According to the petitioner, the respondents illegally raised the water charges from retrospective date and asked for arrears, though enhancement of water charges from a retrospective date is not permissible.
From the affidavits and enclosures filed by the parties, the following fact emerges. The Bokaro Co -operative Society was allotted 90 (ninety) acres of land by the Bokaro
Steel Plant for development and its distribution amongst its members, all of whom were
employees of SAIL, Bokaro Steel Plant. The respondent -Bokaro Steel Plant developed
the entire sewerage and other infrastructural facilities for the establishment of the
Residential House Cooperative Society and also provided all necessary help to he
Bokaro Co -operative Society.
According to the respondents, what initially started as a purely Residential Housing Colony in the Co -operative Society, now it has transpired into a thriving Commercial Complex and losing its residential character violating the terms and conditions of the lease on the basis of which the Bokaro Co -operative Society was handed over with the land.
The water connection was given to the Society by the respondents in the year 1970, which constructed a Captive Dam known as Garga Dam over River Garga and the drinking water was being supplied to all the consumers including the Bokaro Cooperative Society from the said Dam. Over the period of time, the requirement of water in the township having increased, manifold, additional requirement is being met from water taken from the Tenughat Dam/Canal for which the respondents are paying to the State Government towards raw water including cess thereon, at the rate charged by the State Government from time to time.
Initially, vide order plated 18th March, 1970, the rate of Rs. 1.50 per 1000 Gallon was fixed for supply of water to all private consumers including the Bokaro Cooperative Society.
In the year 1977, vide order dated 7 -th September, 1977, an arrangement was arrived at with the Bokaro Co -operative Society for providing some concession in supply of electricity and water. The concession of free supply of water to he Bokaro Co -operative Society equivalent to 12,000 Gallons per month per employee on the rolls of the company having constructed house in the colony was allowed. Beyond this limit, the Co - operative Society was to pay water charges @ Rs. 1.50 per 1000 Gallon.
The respondents revised the water charges for others vide an order dated 17th March, 1994, excepting the HSCL and Bokaro Co -operative Society (petitioner herein). The order, reads as follows : - - STEEL AUTHORITY OF INDIA LTD. BOKARO STEEL PLANT BOKARO STEEL CITY No. 567/A.O. Ref : No. 5 -17(6)94 -5,15 March 17, 1994 OFFICER ORDER Sub : Revision of water charges recoverable from outside parties by T.A. Department. It has been decided to revise the water charges recoverable by T.A. Deppt. from outside parties such as City Centre, Sector Market, Bank Colony etc. (excluding HSCL and Bokaro Steel Em. Co -op. House Constn. Society) as under: - (a) @ Rs. 4.50 (Rs. four and paise fifty only) per 1000 Gal. from 1.4.1992 to 31.10.1993. (b) @ Rs. 6.50 (Rs. Six and paise fifty only) per 1000 Gal. from 1.11.1993 to 31.3.1994, and (c) @ Rs. 7.40 (Rs. Seven and paise forty only) per 1000 Gal. from 1.4.1994 onwards. 3. This issues with the concurrence of Finance and has the approval of the Managing Director. Note : The above rates are subject to review based on actual cost and the rates for HSCL and Bokaro Steel Employees Co op. House Constn. Society shall be worked out separately. Sd/ - (P.K.K. Nair) Manager (L&A)
(3.) ACCORDING to the respondents, a strong objection was raised by the Central Government Audit team with respect to delay in revision of water charges for the petitioner -Bokaro Co -operative
Society.;
Click here to view full judgement.