JUDGEMENT
P.K.BALASUBRAMANYAN, J. -
(1.) THE Bokaro Steel Plant, a Unit of Steel Authority of India Limited is a Government Company within the meaning of Section 617 of the Indian Companies Act, 1956. The Steel Authority of India Limited
(hereinafter referred to as the SAIL) is also a Government Company incorporated with the main object of
manufacturing, prospecting, buying, selling, importing, exporting, or otherwise dealing in iron and steel
of all qualities, types and kinds and in any other steel and iron related products. The Bokaro Steel Plant is
claimed to be a pioneer steel Plant of the country and one of the largest of its kind, having a total
production capacity of 2 million tonnes per year. The steel Plant is covered by a network of gas pipelines,
water network and steam pipelines. It is claimed that the whole system of network of pipelines is
integrated and a very high standard of safety is required to maintain the minimum level of pressure in the
pipelines. The pressure in the pipeline is directly proportional to the production level in the Plant and the
entire steel Plant is maintained at the functional level, so that there is not even an hour of shut down in the
plant. It is claimed that the Bokaro Steel Plant has never been shut down from its very inception. The
Plant is of such a nature that if it is compelled to shut down, it may pose environmental hazards and there
is an apprehension even of human catastrophe. The Plant itself may be very seriously affected if it is shut
down without following the procedures and it requires at least seven days preparation. Even that would be
at the risk of 4,000 tonnes of molten steal in the blast furnaces solidifying and the blast furnaces being
destroyed for ever, leading to the necessity of erecting another at the cost of more than rupees ten
thousand crores, practically compelling the setting up of a new plant. The gas pipeline network may be
damaged leading to escape of lethal gas, carbon monoxide, which, if it escapes, might lead to a tragedy,
loss of human lives like the one in Bhopal. The same would be the position by the damage being caused
to the steam pipelines leading to another catastrophe that may result in loss of lives.
(2.) THE iron and steel industry has been recognized to be the backbone of the country. It has been notified as a public utility service within the meaning of Section 2(n) of the Industrial Disputes Act, 1947. It is
also included in the First Schedule to that Act, containing the industries which may be declared to be the
public utility services in terms of Clause (vi) of Clause (n) of Section 2 of the Act. Item 7 of the Schedule
is 'Iron and Steel'. Section 22 of the Act places restriction on those who are employed in a public utility
service, from resorting to strike without complying with the conditions prescribed therein. The last of the
notifications issued under Section 2(n)(vi) of the Act was by the State of Jharkhand on 16.9.2003.
According to the Bokaro Steel Plant, certain demands were made by the non -recognised Unions. Respondent 6, the recognized Union did not put forward any demand. Considering the importance of the
steel industry and its role in the economy of the nation, a National Joint Committee for the Steel Industry
(for short, NJCS) was constituted in October, 1969. The committee arrived at a settlement and drew up on
27.10.1970 a memorandum of agreement on revision of wages and other benefits in steel industries. In February 1971, the scope of the Committee was enlarged. It was given power to decide its own terms of
reference from day to day and it covered negotiations for wage agreement and its implementation, review
of welfare amenities and facilities, steps to be taken for increase in production, matters on which it was
necessary to draw the attention of the Government and any issue pertaining to the steel industry and its
employees, as may be agreed to in the NJCS from time to time. Thus, the NJCS practically covered all
aspects of the industry, including labour relationship therein and any problem arising out of it. According
to the Bokaro Steel Plant, without resorting to the machinery of NJCS the non -recognised unions gave
them notices of strike along with charters of demand on 10.10.2003. The steel industry immediately
forwarded the said notice to the conciliation officer on 11.10.2003, thus, the conciliation machinery under
the Act was set in motion. But the workers had threatened to go on strike on and from 25.10.2003 in
support of their demands. The Bokaro Steel Limited in that situation approached this Court with the
present writ petition essentially seeking a direction to respondents 7 to 13, the non recognized Unions, to
desist from the strike proposed to be held on 25.10.2003, putting forward the contention that the strike
would be disastrous for the Plant, the environment, human life and also, raising the legal contention that
the strike was illegal, since a conciliation proceeding was pending and no such strike could be resorted to
when the conciliation proceedings are pending in view of the notification issued under Section 2(n) of the
Act. It was also contended that the grievance of the workers, if any, should be taken up through the NJCS.
The strike could result in loss of production leading to national loss. It will also seriously damage the
Plant leading to huge expenditures to put the Plant back on its feet. Though the Court was closed for
Deepawali holidays, the matter was taken up in view of the disaster highlighted by the Plant and an
interim direction was issued on 24.10.2003 restraining the Unions from giving effect to the proposed
strike called for 25.10.2003. The strike was averted, but it is seen that some of the Unions have issued
another notice of their workmen to go ahead with the strike by 11.11.2003. On the Union appearing and
requesting that the matter be heard urgently, the said prayer was acceded to and the writ petition itself was
taken up for hearing as agreed to by both sides, on 13.11.2003.
(3.) ON behalf of the writ petitioner, Sri Deepankar Gupta, Senior Advocate, submitted that the proposed strike was clearly illegal, since it was barred by Section 22 of the Act in view of the fact that the industry
was a public utility service and during the pendency of a conciliation proceeding before the conciliation
officer, no person employed therein, has a right to go on strike. Counsel also contended that the strike was
uncalled for, since the forum available to the union was NJCS, which could deal with all the problems,
including the alleged failure of the Management to implement some of the decisions already taken and in
that situation, the Unions, if they had grievances, could have approached NJCS for resolution. He further
contended that the Unions had no fundamental right to strike. They neither had a statutory right to strike
in the circumstances nor the moral right to strike. Counsel highlighted the disastrous consequences that
may follow an abrupt shut down of the plant if the strike went on and the possible human tragedy of great
magnitude that may visit people of the area. Counsel also highlighted the colossal loss that will be
suffered by the Plant by an abrupt shut down as pleaded in the writ petition. These submissions of the
learned Senior Counsel were met by the learned Senior Counsel for respondent No. 8, who submitted that
the writ petitioner was trying to raise demons without any foundation, for inducing the Court to interfere
at this premature stage and the disastrous consequences projected by the Steel Plant were more imaginary
than real. Of course, Senior Counsel and the other counsel who appeared for various other Unions, could
not positively assert that such consequence as foreseen or projected by the Plant would not occur.
Essentially, the plea was that the Management was exaggerating the possible consequences. There had
been strikes earlier and nothing like the scenario as painted by the Management had presented itself.
Counsel fairly submitted that since this was a public utility service, a strike could not be resorted to in
terms of Section 22 of the Act, during the pendency of the conciliation proceedings. But counsel tried to
argue that the Management was shying away from the conciliation proceedings by trying to raise all sorts
of technical objections. It turned out at the hearing that the Management took the stand before the
conciliation officer that there has to be a separate conciliation proceeding with each union and a combined
conciliation attempt would bear no fruit. Though there were some attempts at conciliation as can be seen
from the rejoinder filed on behalf of the Steel Plant, when the conciliation officer proposed a joint
conciliation conference, the Management took the stand that there could only be individual conciliation
proceeding with each of the Union and raised an objection before the conciliation officer. It is common
ground that the decision of the conciliation officer on that aspect is awaited. Learned Senior Counsel for
the Management submitted before us that if the conciliation officer still took the view that it is be a joint
or common conciliation, the Management was willing to participate in it and the fact of raising a point
that conciliation has to be separate, did not mean that the Management was not participating in the
conciliation proceedings. As noticed, learned counsel for respondent No. 8, supported by other counsel,
essentially took the stand that the Management was not willing to come to the negotiating table and the
strike being a legitimate weapon in the hands of the workers, the Court could not prohibit the strike as
sought for by the Steel Plant. It was also argued that the dispute now raised may not come within the
purview of NJCS and the fact that there is such a forum cannot stand in the way of the workmen asserting
their rights in terms of the Industrial Disputes Act and setting in motion the machinery available under
that Act, including the resort to a strike. Counsel argued that the strike was a legitimate weapon in the
hands of the Union and it is resorted to bring a recalcitrant Management to the negotiating table, so that
the grievances of the workmen could be redressed. There was no reason to interfere at this stage. Counsel
appearing for the other Unions, in addition to supporting the submissions of counsel for respondent No. 8,
also reiterated that it was the reluctance of the Management to come to the negotiating table that led to the
strike notice and if the Management is willing to negotiate, there is no reason why the Unions should go
on strike. The argument of the Senior Counsel for the Steel Plant that the workmen had no legal, moral
right was also sought to be met.;