JUDGEMENT
M.Y. Eqbal, J. -
(1.) IN this writ application the petitioner has prayed for issuance of appropriate writ directing the respondents to treat the contract demand of the petitioner at 10,000 KVA w.e.f. 1st September, 2000 or in the alternative direct the respondents to issue a formal letter of approval enhancing the contract demand from 6,000 KVA to 10,000 KVA w.e.f 1.9.2000 and further a direction be issued to the respondents not to demand any penal charges from September, 2000 because of the excess drawal of power by the petitioner and treating the contract demand at 6,000 KVA.
(2.) THE facts of the case lies in a narrow compass. The petitioner is a industrial unit engaged in manufacturing steel ingots, ferro alloys etc. Since the units of the petitioner are situated within Damodar Valley falling under the command area of Damodar Valley Corporation (DVC), the petitioner entered into an agreement in 1989 with respondent No. 1 for supply of electric energy in bulk. The contract demand was 4,000 KVA which was increased to 5,000 KVA in 1993 and further increased to 6,500 KVA w.e.f. 1995. The contract demand was further increased to 8,000 KVA in 1995 but subsequently reduced to 6,000 KVA w.e.f. 8.1.1999. The petitioner's case is that on 12.5.2000 DVC served a notice for revision of power supply operation to the petitioner which was made effective from 1st September, 2000. On 29th August, 2000 the petitioner by letter requested the respondent to increase its contractual demand from 6,000 KVA to 10,000 KVA w.e.f. 1st September, 2000 in view of the enhanced power requirement in its Ferro Alloys Steel Plant. It is stated that thereafter a Senior Divisional Manager and Executive Engineer visited the factory premises of the petitioner on 30.9.2000 and changed the CT ratio of the petitioner from 150/5 to 300/5 to enable it to take the load at 10,000 KVA and above. A joint report was drawn and signed by the officers of the DVC and the representative of the petitioner. The petitioner's further case is that on the changed CT ratio the petitioner understood that it was done with the approval of the competent authority and will amount to enhancing the contract demand from 6,000 KVA to 10,000 KVA. The petitioner thereafter requested the respondent to give a formal sanction of increasing the contract demand as aforesaid. It is alleged that in -spite of several letters and reminders the respondents have not issued a formal sanction letter. On the contrary in absence of formal sanction letter respondents are charging penal contract demand charges @ 401.50 KVA in place of normal demand charges @ 365 per KVA on the ground that the petitioner is exceeding the contract demand. The petitioner claims that the respondents are not entitled to charge penal demand charges at the rate aforesaid and the excess amount paid by it is liable to be adjusted.
(3.) THE stand of the respondents in the counter affidavit is that the petitioner desired to enhance their contract demand form 6,000 KVA to 10,000 KVA in order to run their different industry namely Gautam Ferro Alloys Limited for which there is no agreement with the respondents for the supply of electricity. The petitioner illegally extended the electrical power to Gautam Ferro Alloys Limited violating the agreement for which the respondents had disconnected the power supply of Gautam Ferro Alloys Limited. The petitioner thereafter accepted the illegality and agreed to pay the penal charges. On payment of penal charges the power supply was re -connected. It is stated by the respondents that taking advantage of re -connection the petitioner filed a suit in the Court of Munsif, Hazaribagh for grant of injunction restraining the respondent from taking any penal action/disconnection and obtained an interim order of status quo passed by the Munsif, Hazaribagh in Title Suit No. 112/ 2000 ultimately set aside by the District Judge, Hazaribagh in Miscellaneous Appeal No. 2/2000. The petitioner thereafter filed writ petition being WPC No. 5129/2000 and the same was ultimately withdrawn. The petitioner then filed civil revision before this Court being CR No. 344/2000. In the said revision application the petitioner agreed that it will take a separate connection for M/s Gautam Ferro Alloys Limited and for which the petitioner is ready to deposit the necessary amount for fresh connection. In terms of the aforesaid agreement the civil revision application was disposed of. Pursuant to the aforesaid order the petitioner applied for a fresh connection to M/s Gautam Ferro Alloys with a contract demand of 3,000 KVA and further requested to reduce the demand of the petitioner unit from 10,000 KVA to 3,500 KVA. The case of the respondent therefore, is that for the excess drawal of electricity beyond the contract demand i.e. beyond 6,000 KVA, the respondents are entitled to charge penal rate as per the schedule. It is stated that the changing of CT ratio does not mean increase/revision of the demand of any consumer. The changing of CT ratio is a matter of power system activity on the basis of operating condition. Whenever there is any over loading in any section of system and the CT ratio is found to be inadequate for safety of the system, the CT ratio is changed for smooth operation of Damodar Valley Corporation transmission system.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.