JUDGEMENT
M.Y. Eqbal, J. -
(1.) This appeal under Section 39 of the Arbitration Act, 1940 is directed
against the judgment and decree dated
5.5.2001 passed by Sub-Judge, 1st Bokaro at
Chas in Title Arbitration Suit No.4 of 1998,
whereby he has confirmed the Award dated
16.2.1998 given by the Arbitrator and rejected
the application filed by the appellant under
Section 30 of the said Act for setting aside the
Award.
(2.) The facts of the case lie in a narrow
compass.
(3.) The appellant floated a tender notice
dated 4.1.1982 inviting quotation for construction of
Community Hall in Sector VIII. Pursuant to the said tender notice, the respondent
submitted quotation which was accepted and
letter of intent was issued by the appellant on
12.5.1982 and an agreement was signed on
15.7.1982. In terms of the agreement the
period of completion of work Was 10 months
to be reckon after 15 days from the date of
issuance of letter of intent or actual start of
the work whichever be earlier. The respondents was required to complete and hand-over
the work in phase manner.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.