JUDGEMENT
Gurusharan Shartna,J. -
(1.) Heard the
parties and perused lower Court records This
appeal under Section 39(1 )(vi) of the Arbitration Act, 1940 (hereinafter referred to as 'the
Act') has been filed against judgment/order
dated 29 6 1999, passed by 3rd Subordinate
Judge, Palamue at Daltanganj in Title Suit No
10 of 1992. whereby award dated 2.11.1995
was set-aside and the matter was referred to
another Arbitrator for fresh adjudication after
hearing the parties and obtaining proposal for
fresh Arbitrator, in term of Agreement No. 61/A-F-2 of 1987-88
The agreement in question was for construction of Auranga Right
Mam Canal RD 35 20 to RD 36.90. Stipulated date to complete the work was
26 2 1990 Altogether the contractor raised
five items of claims A sum of Rs. 55,000/-
against claim No. 1 for loss of advance on
material, labour etc ; a sum of Rs.7,47,170/-
against claim No 2 for loss of idle labour, plant
and equipment; a sum of Rs. 2,28,000/-
against claim No. 3 for compensation for
infructuous cost of overhead establishment etc.,
and a sum of Rs 2,28,000/- against claim
No 5 for loss of profit on the work, which
could not be executed and thus altogether total amount of Rs 12,58,170/- was awarded
with interest @ 12% per annum from 1 8 1991
onward till the date of award
(2.) A perusal of the award revealed that it
was a non-speaking and unreasoned award
(3.) The main objection to the award was
whether the Arbitrator had misconducted in
conducting the arbitration proceeding and had
committed any error of fact in passing the
award in question.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.