JUDGEMENT
-
(1.) The petitioner has challenged the allotment of work under
allotment letter no. 1/PMC/Work/572/08-78 Ranchi dated 29.6.2009 in
favour of respondent no. 5 and for direction to allot the said work to
the petitioner.
(2.) Mr. Anil Kumar Sinha, Senior counsel appearing for the petitioner
referring to the decision of the tender committee dated 11.11.2008
submitted that all the bids including that of petitioner and respondent
no. 5 were found valid but the petitioner was denied allotment of the
work on the ground that out of four works already allotted to the
petitioner, progress in two works were found unsatisfactory i.e. 40.51%
and 25% though the petitioner was senior-most and local contractor;
and work was allotted in favour of respondent no. 5 only on the ground
that there was satisfactory progress to the extent of 75.06% in another
work allotted to him. He referred to Clause 16 of Jharkhand Enlistment
of Contractors Rules, 2001 (for short "the Rules"). He further submitted
that the work in progress with regard to the earlier work given to
respondent no. 5 has been taken to be 75.06% including the materials
brought at the site by respondent no. 5 and, therefore, it cannot be
said that he had completed the work up to 75%. He further submitted
that respondent no. 5 has manipulated the reports for ousting the
petitioner and getting the allotment in his favour.
Mr. P.K. Prasad, learned Advocate General, appearing for
respondents no. 1 to 4 and Mr. Sumeet Gadodia, learned counsel
appearing for respondent no. 5 denied and disputed the stand taken by
Mr. Sinha, appearing for the petitioner and supported the decision of
the tender committee. They, inter alia, relied on the judgment of
Raunaq International Ltd. vs. I.V.R. Construction Ltd. and others, 1999 AIR(SC) 393 and Master Marine services (P) Ltd. vs.
Metcalfe & Hodgkinson (P) Ltd. and another, 2005 6 SCC 138.
(3.) After hearing the counsel appearing on behalf of the parties and
on going through the records, I find no reason to interfere with the
decision making process in awarding work to respondent no. 5. Clause
16 of the Rules reads as under:-
"16. The contractor will be generally allotted one work at a time. Even if
they are valid and lowest tenderer in an other bids, until and unless they
complete the work allotted to them or the progress of work is at least upto
seventy-five percent. No other work will be allotted to him.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.