JUDGEMENT
-
(1.) Learned counsel appearing for the petitioner submitted that the
respondents have issued the electricity consumption bills for the months
of April, May and October 2008 without any basis and the impugned bills
have been issued for the said period, for which, the meter of the electricity
was not properly functioning. It is also submitted by learned counsel for
the petitioner that a letter was written in the month of November 2005 to
the respondents that the meter is not properly functioning and it requires
to be changed. Despite this letter, no action was initiated by the
respondents and ultimately, the meter was replaced by the new meter on
26th August, 2007 and the bills, which have been issued for the
intervening period from November 2005 onwards is having no basis at
all. It is also submitted by learned counsel for the petitioner that there are
several decisions rendered by this Court that whenever meter is found
defective and it is replaced later on, on the basis of the average
consumption of the earlier meter and when it was working properly,
should be calculated on the basis of the average of three months of a new
meter bills, should be considered by the respondents. None of the
methods have been followed by the respondents, therefore, the impugned
bills for the months of April, May and October 2008 deserve to be
quashed and set aside.
(2.) I have heard learned counsel for the respondent-J.S.E.B., who has
submitted that the petitioner is not remedy-less and the efficacious
alternative remedy is available to the petitioner under sub-Section 5 of
Section 42 of the Electricity Act, 2003 (hereinafter to be referred to as the
Act, 2003). In pursuance of the aforesaid sub-Section 5 of Section 42 of
the Act, 2003, a Forum/Committee has been constituted and before the
Forum/Committee, which is known as "V.U.S.N.F.", the petitioner can
ventilate his grievances and not only this, but, the said order based under
sub-Section 5 of Section 42 of the Act, 2003 is also appellable under sub-
Section 6 of Section 42 of the Act, 2003. Thus, under the provisions of
the Act, 2003, there is also inbuilt mechanism of the appeal and,
therefore, let the petitioner may approach the said Forum/Committee
under sub-Section 5 of Section 42 of the Act, 2003 and, thereafter, under
sub-Section 6 of Section 42 of the Act, 2003 so that the grievances
ventilated in this petition can be brought to an end, thereafter, it is always
open with the petitioner to approach this Court in case of further or left
out grievances.
(3.) In view of the aforesaid submissions and looking to the sub-Section
5 of Section 42 of the Act, 2003, it appears that the petitioner is not
remedy-less. The electricity bills, which are challenged before this Court
for the months of April, May and October 2008 can always be very well
challenged before a Forum/Committee, constituted under sub-Section 5 of
Section 42 of the Act, 2003. Moreover, if the petitioner is aggrieved by
the order passed under sub-Section 5 of Section 42 of the Act, 2003, then
appeal is also provided under sub-Section 6 of Section 42 of the Act,
2003. Thus, efficacious alternative remedy is available to the petitioner.
Hence, I hereby permit the petitioner to prefer necessary application or
objection under sub-Section 5 of Section 42 of the Act, 2003 before the
Forum/Committee constituted thereunder and I hereby also direct the said
Forum/Committee, which is known as "V.U.S.N.F." to hear the petitioner
or to his representative and decide the said application/objection against
the bills for the months of April, May and October 2008, in accordance
with law, rules, regulations, policy and Government enforceable orders
and if the petitioner is aggrieved by the order under sub-Section 5 of
Section 42 of the Act, 2003, still there is provision of appeal under sub-
Section 6 of Section 42 of the Act, 2003 thereof. If the
application/objection is preferred under sub-Section 5 of Section 42 of the
Act, 2003, the same will be decided as expeditiously as possible and
practicable by the said Forum/Committee, which is known as
"V.U.S.N.F.".;