J.P. DEVELOPERS Vs. RAJASTHAN STATE ROAD DEVELOPMENT AND CONSTRUCTION
LAWS(RAJ)-2019-9-86
HIGH COURT OF RAJASTHAN
Decided on September 02,2019

J.P. Developers Appellant
VERSUS
Rajasthan State Road Development And Construction Respondents

JUDGEMENT

- (1.) This petition has been filed with the prayer to quash and set aside the impugned letter dated 29.7.2019 requiring certain deposits and Bank Guarantees as also post dated cheques as per the conditions of the NIT dated 13.6.2019 for collection of toll tax where the petitioner's bid had been accepted and inter-alia direct the respondents to provide reasonable time to the petitioner for depositing requisite payments as per the bid. It has been further prayed that the respondents be directed not to award the tender for collection of toll tax under the NIT dated 13.6.2019 to any other contractor for which the petitioner alone is entitled being the highest bidder.
(2.) Mr. Sandeep Singh Shekhawat, counsel for the petitioner submitted that the respondents issued an E-NIT dated 13.6.2019 for collection of toll tax on Bundi Bijoliya Section of Khatkar Bundi Bijoliya Road (hereafter 'the Road") for 2 years with reserve price of Rs. 233.50 lakh. He submitted that when the NIT was notified the road was incomplete and the participants in the bidding process were orally informed that the road under construction would be completed prior to execution of the contract in favour of the highest bidder. The petitioner participated in the bidding process and being the highest bidder was declared successful. Consequent to which the impugned letter dated 29.7.2019 followed. Mr. Sandeep Singh Shekhawat submitted that, albeit the petitioner has been awarded the contract for toll collection but the road is still incomplete, as a result of which vehicles are not being plied on the road. The grant of the contract for collection of toll on such a road is presently a futility which will only entail the petitioner's obligation to deposit amounts under the impugned letter and further render it vulnerable to huge financial obligations without the contracted recompense. It has been submitted that vide the impugned letter dated 29.7.2019, the petitioner is to deposit one installment for the above toll collection contract @ 8% of the bid amount i.e. Rs. 22,48,889/- plus TCS @ 2% amounting to Rs. 44,978/-, aggregating to a sum of Rs. 22,93,867/- by Demand Draft and Performance Bank Guarantee @ 15% of the Bid Amount i.e. Rs. 42,16,667/- from Nationalized Bank within ten days i.e. by 8.8.2019 aside of depositing 23 post dated cheques against remainder 23 monthly installments covering the bid amount. Non compliance will entail cancellation of the bid and forfeiture of earnest money amount. Hence till the road on which toll is to be collected is complete, it be directed that the petitioner be protected and the respondents be directed not to make any unjust arbitrary demand as under the impugned letter dated 29.7.2019.
(3.) Mr. VP Mathur, counsel for the respondents submitted that following the impugned letter dated 29.7.2019, an agreement dated 31.7.2019 was executed by the petitioner with the Rajasthan State Road Development and Construction Corporation (RSRDCC). The petition is therefore infructuous. As per clause 9 of the said Agreement dated 31.7.2019, the petitioner if aggrieved of the working of the contract for collection of toll on the road in issue on any count, including the road allegedly being incomplete in breach of the respondent's obligation, the petitioner is required to approach the Empowered Standing Committee for resolution of the dispute arising therefrom. Instead of approaching the Empowered Standing Committee, the petitioner seeks to ill- advisedly pursue his grievance in respect of a matter of pure contract before this Court. In the circumstance, the writ petition is not maintainable and to be dismissed - moreso it agitates a pure question of fact in the realm of a contractual dispute without any iota of public law element. On the falsity of the petitioner's claim, it has been submitted that in fact traffic is regularly plying on the road in question without obstruction. The road, for which the petitioner's bid for collection of toll was accepted is complete except for a portion of only 800 mtrs. pertaining to a minor bridge alongwith its approaches in respect of which an alternate motorable bye pass has been made whereon the traffic is plying regularly without any obstruction. There is no obstruction to the collection of toll.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.