JUDGEMENT
Shiv Kumar Sharma, J. -
(1.) Both these
appeals arise from the judgment and decree
dated November 15, 1994 passed by the
Additional District Judge No. 1, Bharatpur,
making the award a rule of the court.
(2.) The relevant facts in brief, which have
given rise to these appeals, are that M/s. Alim
and Company (for short the Company) entered into a contract with the State of Rajasthan
(for short the State) for the work of construction of high level bridge over river 'Banjara'
on Jaipur Agra Road, National Highway No.
11, Kilometre 96/0/0 at Agra under
Agreement No 19 of 1982-83 for a sum of Rs
1,07,83,700/- The disputes which arose in
respect of the said contract were referred to
the sole Arbitrator Shri Man Mohan Singh
retired Additional Chief Engineer, P.W D.
Rajasthan, who passed the award on August
29, 1991 by which Company's claim to the
extent of Rs. 1,21,421.94 was allowed besides other directions regarding release of the
performance guarantor bond and the other
bank guarantee. The Arbitrator had also allowed the future interest @ 18 per cent from
the date of award upto the actual payment or
the date of decree whichever is earlier for
making the award, a rule of the court under
Section 17 of the Arbitration Act, 1940 (for
short the Act). The Company filed an application under Sections 14, 17 and 29 of the
Act before the District Judge, Bharatpur which
was later on transferred to the court of Additional District Judge Court No. 1, Bharatpur
who made the award a rule of the court.
(3.) The Company has challenged the
impugned judgment and decree on the ground
that the court acted illegally in reducing the
interest from 18% to 12% per annum and also
urged that direction regarding the bank guarantee be ordered to be set aside. Whereas the
contention of the State is that entire judgment
deserves to be quashed. Mr. K.S. Rathore,
learned Additional Advocate General for the
State canvassed that the court below had
ignored the counter claim objections filed by
the State. The Arbitrator has wrongly awarded
the claim of Rs. 12,48,643.60 towards the
escalation in terms of Clause 45 of the printed
agreement PWD MF 107 inducted on September 21, 1983 subsequently disregarding
the explicit contractual provision existing in
the agreement in terms of Clause 60 of the
Agreement No. 19. In fact escalation as per
provision of Clause 60 of the original agreement No. 19 of 1982-83 was paid to the
Company which was accepted by it without
objection but the court below failed to appreciate this important aspect. The learned court
below also failed to consider that Clause did
not exist in the original agreement No 19 of
82-83 and the observation of the Arbitrator
that remedy was available to the Company
under the said Clause was against the record.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.