JUDGEMENT
KANWALJIT SINGH AHLUWALIA,J. -
(1.) Instant appeal has been
instituted by the defendant-appellants, namely Rajasthan State
Cooperative Bank Limited, Jaipur through its Managing Director, in order
to assail the impugned judgment and decree dated 03.06.1995 rendered by
the Court of Additional District Judge, Sikar, whereby the suit of the
plaintiff-respondent was decreed for Rs. 13,402/-.
(2.) Ramvatar Sharma, plaintiff-respondent No. 1, herein is a work contractor. Way back on 08/12.03.1983, he was awarded construction work
of 100 MT Godown (residence) at G.S.S. Kotri Shimarla, Police Station
Srimadhopur District Sikar (Rajasthan). In the work order, he was asked
to carry out the work upto an amount of Rs. 81,771/-. The work order
(Exhibit/2) further stated that work allotted will be restricted upto Rs.
70,666/-. A condition was also specified in the work order that the work is to be completed within a period of four-&-half months from the date of
issuance of the work order.
(3.) Mr. J.K. Singhi, learned senior counsel, ably assisted by Mr. Amitabh Jatav, ld. counsel appearing for the defendant-appellants, has submitted
that the plaintiff-respondents had not started the work within
four-&-half months, the period stipulated for the completion of the work.
It is contended that after giving repeated reminders, execution of the
work started in the month of July, 1983. Ld. senior counsel has further
submitted that after completing the work upto Rs. 70,666/-, contractors
stopped the work and later-on, the wooden work was to be awarded to
another contractor and, hence, the delay had occurred in execution of the
contractor.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.