JUDGEMENT
-
(1.) The applicant M/s. Pioneer
Construction has filed this application for
appointment of an arbitrator in regard to a
dispute which he has raised claiming additional amount
on account of price escalation of the materials which he had used in
construction of the quarters to be used as
residence by the Judicial Officers.
(2.) To appreciate the controversy it may
be noticed that a contract was awarded to
the applicant in the year 1995 for construction of residential
accommodation for judicial officers by the Public Works Department
of the Government of Rajasthan which was
to be completed by 23-4-1996. But the petitioner executed the contract finally in the
year 1998 for which the entire payment also
was made to the applicant in the year 1998
itself. The applicant however had a late
realisation in the year 2001 when it struck
him that he could claim additional payment
in regard to the contract which he had executed in
the year 1998 towards price escalation taking the advantage of an order for
increase in petroleum products and therefore, he filed an application after five years
of acceptance of final payment in the year
2003 for appointment of an arbitrator in
regard to additional claim of payment towards price escalation of
petroleum products which he had used in construction of
the residential premises.
(3.) While filing an application for appointment of an arbitrator the applicant and his
counsel have totally ignored the agreement
which had been executed between the applicant and the respondent-State in regard
to execution of the contract as admittedly
the clause regarding price escalation had
been specifically deleted in the agreement
to which the applicant had agreed by
signing the agreement. It is therefore, relevant
to quote Clause 45 of the agreement which
lays down as follows :
"Clause 45. If, during the progress of the
contract of value exceeding Rs. 10.00 lac
(accepted tendered amount minus cost of
material supplied by the department), and
where stipulated completion period is more
than 12 months (both the conditions should
be fulfilled) the price, of any materials/bitumen/diesel and petrol incorporated in the
works (not being materials supplied by the
Department) and/or wages of labour increase or decreases, as compared to the price
and/or wages prevailing at the date of opening of tender or date of negotiations for the
work, the amount payable to contractors for
the work shall be adjusted for increase or
decrease in the rates of materials (excepting those materials supplied by
the Department/labour/bitumen diesel and petrol. If
negotiated rates have been accepted, prices
as on the date of negotiation shall be considered for price adjustment. Similarly, if
rates received on the date of opening of
tenders have been accepted, them prices on the
date of opening of tender shall be considered for price adjustment.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.