JUDGEMENT
-
(1.) IN assailment is the judgment and order dated 28.3.2014
passed in S.B.Civil Writ Petition No.747/2014 thereby alongwith
that writ petition, S.B.Civil Writ Petition No.767/2014 was also
dismissed.
(2.) WE have heard Mr.Sandeep Shah, learned counsel for the
appellants -writ -petitioners.
The facts in bare minimum are that the appellants -writ -
petitioners claimed to be possessed of agricultural land included in
khasras no.761 and 771 situated in village Peshua, Tehsil Pindwara
District Sirohi. According to them, about a decade ago, 132 KV line
was drawn over this land by the respondent -Nigam so as to
facilitate supply of power to J.K.Cement Industry for which certain
poles/pillars were installed thereon. The appellants -writ -
petitioners averred that though they objected to the project and
claimed compensation, their requests were not heeded to. They
have averred further that the high tension power line and the
energy flow does create a strong magnetic field, so much so that
no cultivation/agricultural exploit is possible in the vicinity
thereof. Further, there is a constant risk to life and property. The
appellants -writ -petitioners have averred that adjoining their
agricultural land, there is an existing railway track and that in view
of broadening thereof to four tracks, relocation of the wires of 132
KV line existing on their land is proposed. According to them, the
respondent -authorities accordingly visited their land and inspected
the site and on enquries being made they were told that new
towers were to be installed. They however refused to disclose the
details of such installations, but confirmed that the work as
proposed would be carried out. Referring to a work order dated
(3.) 12.2013 and the connected map, the appellants -writ -petitioners contended that new towers for stepped up power transmission
would be erected for which there would be massive excavation of
their land. That the respondents -authorities had turned a deaf ear
to their pleas citing damage to their land, crops thereon and
overall safety and instead had communicated that police assistance
would be requisitioned if need be for execution of the project,
have been stated. Contending that the contemplated action is
illegal, the appellants -writ -petitioners sought judicial intervention.
The respondents in their reply clarified that the existing
transmission line was not meant for supply of power to M/s
J.K.Cement Industry as alleged, but was to cater to the need of
the public at large of Abu Road. Pleading that on account of
alteration in the railway tracks some more towers/poles have
become necessary to be installed, the respondents have denied
that there is any proposal to set up 220 KV transmission line as
apprehended by the appellants -writ -petitioners. According to
them, the project in hand is for re -location of the presently
existing transmission lines and the project has been undertaken in
consultation and with the consent of the Railway Administration.
Referring to Section 164 of The Electricity Act, 2003 (for short,
hereinafter referred to as "the Act") and sections 10 and 16 of The
Indian Telegraph Act, 1885 (for short, hereafter referred to as "the
1885 Act"), the respondents have pleaded that neither any prior consent nor notice nor intimation to the owner or occupier of the
immovable property is a condition precedent for undertaking the
project as contemplated and that for computation and payment of
compensation, a civil forum has been provided and thus, the cavil
pertaining thereto is also without any substance.
4. Whereas the appellants -writ -petitioners in their rejoinder
contended that reliance on section 164 of the Act and sections 10
and 16 of 1885 Act was wholly inconsequential, the respondents by
their additional affidavit brought on record the notifications dated;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.