JUDGEMENT
-
(1.) THIS petition for writ is directed to challenge
the orders dated 8.2.2008, 17.4.2008 and 27.3.2012 passed
by the Divisional Irrigation Officer (Executive Engineer),
Water Resources Division -II, Hanumangarh; the
Superintending Engineer, Water Resources Circle,
Hanumangarh and the Collector, Sriganganagar respectively.
By the order 8.2.2008 the Divisional Irrigation Officer
(Executive Engineer) accepted an application preferred by
respondents Sarva Shri Mamraj, Dhanraj, Krishna Lal, Vinod
Kumar and Buddhram for transfer of their 'Rakba' to Chak 9
DBM from Chak 24 LGW. The Divisional Irrigation Officer
also ordered for providing water course to the respondents
named above from the main water course available with 9
DBM. The orders passed by the Superintending Engineer and
the Collector are the orders affirming the order passed by
the Divisional Irrigation Officer (Executive Engineer).
(2.) THE facts necessary to be noticed are that respondents Sarva Shri Mamraj and Dhanraj preferred
applications in the month of January, 2006 to the Executive
Engineer, Irrigation Division -II, Hanumangarh Junction for
transfer of their land to Chak 9 DBM from Chak 24 LGW. The
transfer was sought on the count that they were not
receiving adequate water from the water course available
with Chak 24 LGW. The Executive Engineer in the capacity of
the Divisional Irrigation Officer issued general notices
inviting objections for the transfer sought to be made by
the private respondents. Several agriculturists of Chak 9
DBM objected for demanded transfer, but the Divisional
Irrigation Officer made an order dated 8.2.2008 for
transfer as desired by the private respondents and also
allowed irrigation facility.
Aggrieved by the order passed by the Divisional
Irrigation Officer, the petitioner and several other
agriculturists preferred appeal before the Superintending
Engineer, Water Resources Circle, Hanumangarh and that also
came to be rejected on 17.4.2008. The private respondents
then moved an application before the Collector to execute
the decision taken by the Divisional Irrigation Officer.
The petitioner also submitted objections with specific
assertion that more than 68% of the agriculturists of Chak
9 DBM are not agreeable for the transfer. Several other objections too were taken by the petitioner including the
procedural illegality accepting in awarding transfer of the
land to Chak 9 DBM. A prayer was also made to treat the
memo of objections as a petition under Section 24 of the
Rajasthan Irrigation and Drainage Act, 1954 (hereinafter
referred to as 'the Act of 1954').
The Collector by the order dated 27.3.2012 affirmed the order dated 8.2.2008 passed by the Divisional
Irrigation Officer on the count that the order was passed
after hearing the petitioner and the petitioner did not
challenge the findings given by the Divisional Irrigation
Officer either by way of filing appeal or by way of filing
a petition for writ before the High Court. The Collector
treated the order passed by the Divisional Irrigation
Officer (Executive Engineer) dated 8.2.2008 a final, thus,
directed to provide water course to the private respondents
in Chak 9 DBM and to close the water course from Chak 24
LGW.
While challenging the order passed by the
Divisional Irrigation Officer, the Superintending Engineer
and the Collector, the submission of learned counsel for
the petitioner is that as per the procedure given for
transfer of existing water course, the decision would have
been taken by the Collector by conducting an inquiry and
not by the Divisional Irrigation Officer. As per learned
counsel for the petitioner the procedure adopted in the
instant matter is contrary to the procedure prescribed
under Sections 23 and 24 of the Act of 1954. The other
argument advanced is that even by assuming that the
procedure adopted was in consonance with the provisions of
the Act of 1954, then too the Collector while exercising
authority under Section 24 of the Act should have given
adequate reasons for not accepting the objections raised by
the petitioner.
(3.) PER contra, as per counsel for the respondents, the private respondents submitted application to the
Divisional Irrigation Officer for transfer of existing
water course in accordance with sub -section (1) of Section
23 of the Act of 1954 and the Divisional Irrigation Officer after holding necessary inquiry found the transfer
necessary for the better management of the irrigation,
thus, passed the order dated 8.2.2008. It is asserted that
the Collector has given adequate reasons for accepting the
findings arrived by the Divisional Irrigation Officer.
Heard learned counsel for the parties and
considered the rival submissions.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.