JUDGEMENT
Pratap Krishna Lohra, J. -
(1.) MATTER comes up on second stay petition but with the consent of both the parties, appeal itself is heard finally at this stage and disposed of by this judgment. Appalled by the order dt. 4.3.2013, the appellants have laid this appeal under Sec. 37 of the Arbitration and Conciliation Act, 1996 (for short, 'Act of 1996) By the order impugned, learned Additional District Judge No. 3, Udaipur has rejected the application of the appellants under Sec. 34 of the Act of 1996 by declining to interfere with the arbitral award dt. 21.4.2010.
(2.) SUCCINCTLY stated, the facts of the case are that State Government sanctioned the work for construction of flow portion of RD 235 to 3501 M of Chiklawas Irrigation Project by its order dt. 7.3.1994 for a sum of Rs. 3,32,15,276/ - in favour of appellant -Corporation and in this respect Work Order was issued and requisite agreement was also executed. Pursuant to the Work Order, appellants issued a Notice Inviting Tender (for short, 'NIT') in which respondent also participated and after acceptance of its tender. Work Order No. 10/97 dt. 2.5.1994 was issued for a sum of Rs. 1,79,52,393.09. The aforesaid work was allotted to the respondent on the same terms and conditions, which were agreed between the appellants and the Irrigation Department. In the Work Order, the date of commencement of the work was mentioned as 15.5.1994 and deadline for its completion was shown as 14.11.1995. However, in fact, the work was completed on 18.6.1997. After completion of the work, a dispute cropped up between the parties and eventually by judicial intervention, at the behest of respondent, this Court, while exercising powers under Sec. 18 of the Act of 1996, appointed Arbitrator vide order dt. 5.5.2005 while deciding S.B. Civil Arbitration Application No. 42/2004. The respondent contractor submitted its claim before the sole Arbitrator worth Rs. 1,53,29,794.18, while dividing it in 13 parts. The details about 13 claims of the respondent are as under: - -
Claim No -1
Refund of Security Deposit (SD) for Rs. 5,30,000.00 (Rupees five lacs thirty thousand).
Claim No. 2
Payment of Final Bill for Rs. 10,14,711.00 (Rupees ten lacs fourteen thousand seven hundred eleven).
Claim No. 3
Escalation charges for labour and material for Rs. 11,91,776.18 (Rupees eleven lacs ninety one thousand seven hundred seventy six & paise eighteen) as per Agreement Clause 45.
Claim No. 4
Overhead expenditure and reduced profitability for Rs. 14,07,000.00 (Rupees fourteen lacs seven thousand).
Claim No. 5
Idling of labour and machinery for Rs. 66,50,000.00 (Rupees sixty six lacs fifty thousand).
Claim No. 6
Reduced profitability - Claim for Rs. 16,10,991.00 (Rupees sixteen lacs ten thousand nine hundred ninety one).
Claim No. 7
Increase in minimum wages claim for Rs. 3,95,366.00 (Rupees three lacs ninety five thousand three hundred sixty six).
Claim No. 8
Payment for land acquisition for haul road Rs. 1,57,000.00 (Rupees one lac fifty seven thousand).
Claim No. 9
Payment for cleaning of blocks Rs. 38,000.00 (Rupees thirty eight thousand).
Claim No. 10
Construction of temporary access on block No. 14 Rs. 40,000.00 (Rupees forty thousand)
Claim No. 11
Wrong recovery of Rs. 35,000.00 (Rupees thirty five thousand) for electric connection.
Claim No. 12
Illegal and wrongful deduction of Rs. 7,60,000.00 (Rupees seven lacs sixty thousand) from running bills.
Claim No. 13
Damage for illegal & wrongful deductions, non payments etc. - Rs. 15,00,000.00 (Rupees fifteen lacs)
For substantiating the aforementioned claims, the respondent pleaded requisite facts in the claim petition and also produced documentary evidence.
(3.) RESPONDING to the claim petition submitted by the respondent -contractor, appellants filed a reply. In the return, respondent has raised a preliminary objection that entire work relates to the Irrigation Department, and therefore, without impleadment of Irrigation Department, claim cannot be processed. In the reply, it was also pleaded that delay in completion of work is directly attributable to the Irrigation Department and time was extended by Chief Engineer, Irrigation Department for completion of work, therefore, detailed reply in this behalf can be by filed by the Irrigation Department. The sole Arbitrator framed in all 18 points for determination between the rival parties and after completion of evidence passed; Award on 21.4.2010 favouring the respondent -contractor. The sole Arbitrator passed the award following terms: - -
In accordance with the decision of the various issues, an Award in favour of the claimants and against the respondents is passed as under:
1. The Principal amount of Rs. 74,36,130/ - (Rupees seventy four lacs thirty six thousand one hundred thirty).
1(a) An amount of Rs. 45,67,413/ - (Rupees forty five lacs sixty seven thousand four hundred thirteen) as interest at the rate of 9% per annum on the above amount from 3.8.1999 upto 31.5.2006.
Total amount Rs. 1,20,03,543/ - (Rupees one crore twenty lacs three thousand five hundred forty three).
2. Interest at the rate 9% per annum on the principal amount of the Award i.e. the amount of Rs. 74,36,130/ - (Rupees seventy four lacs thirty six thousand one hundred thirty) pendent lite and future till realization of the total amount of the Award.;