JUDGEMENT
-
(1.) THE order dated 10.09.2012, passed on the application filed under Article 226(3) of the Constitution of India for vacation of the
interim order dated 01.10.2010 in S.B. Civil Writ Petition No.12745/2010,
is under challenge in the present appeal.
(2.) THE appellant is the petitioner in S.B. Civil Writ Petition No.12745/2010. By the order impugned, the writ -petition has been
disposed of by relegating the writ -petitioner to the remedy of appeal
under Rule 43 of the Rajasthan Minor Mineral Concession Rules, 1986 (for
short, hereafter referred to as 'the Rules'). The stay application filed by
him stood rejected thereby as well.
We have heard Mr. Vimal Choudhary, the learned counsel for the appellants and Mr. N.S. Chauhan, Deputy Government Counsel for the
State -respondents.
(3.) A brief account of the relevant facts, to the extent indispensable for the present adjudication, is called for. The
appellant/writ -petitioner had been granted mining lease for mineral
masonry stone for an area measuring 10000 sq. meters near village Badi
Doongari, Tehsil Phulera, District Jaipur by order dated 08.12.1994 for a
period of 20 years from the date of registration of the lease deed. The
mining lease came into force with effect from 08.05.1995, the date of
registration of the lease deed and was to continue for a period of 20
years, as aforestated. According to the appellant/writ -petitioner, he had
been strictly adhering to the terms and conditions of the lease and was
abiding by all the requirements prescribed thereby. He has asserted that
he had been submitting the returns, as required, and the amount of
royalty in terms thereof. Contending that from the very beginning he has
been facing problem of illegal excavation by unauthorized persons in the
sites abutting his mining area, the appellant/writ -petitioner has stated
that complaining about the same, he had submitted several
representations before the concerned Mining Engineer. That eventually
on 11.08.2006 his mining operations had to be closed down and that
thereafter the same has not been restored, has been stated by him. The
appellant/writ -petitioner has also referred to the motivated complaints
made by the villagers with the concerned authorities of the Mining
Department for cancellation of his mining lease. According to him, being
apprehensive of adverse action against him, he instituted a suit in the
Court of Civil Judge (Junior Division), Court No.2, Jaipur City, Jaipur,
praying for a decree of permanent injunction. He has stated that on the
application under Order 39 Rule 1 and 2 CPC, the learned trial Court, on
26.08.2006, passed an order maintaining status quo. He, however, has alleged that in spite of such judicial intervention, unauthorized and
unfounded complaints against him continued to be filed. He has referred
as well to a public interest litigation, initiated before this Court i.e. D.B.
Civil Writ Petition No.8422/2006 by the villagers, in which the State -
respondents, in their reply, categorically pleaded against any breach
committed by him of the terms and conditions of the lease or illegal
excavation. This proceeding was eventually disposed on 18.09.2007. This,
notwithstanding, in the face of the unabated complaints being filed
against the appellant with ulterior motive, an ex parte inspection of the
site was carried out on 22.12.2007, whereupon the jurisdictional Mining
Engineer issued a notice on 02.01.2008 asking him to be present for
demarcation on 18.01.2008. According to the appellant/writ -petitioner,
in spite of his representations seeking time, the same were cast aside
and an inspection was conducted on 25.02.2008 in his absence,
whereafter a notice was issued 26.03.2008 to him alleging that he had
been carrying on illegal excavation of masonry stone outside the
sanctioned area of mining lease. Being aggrieved by this step and also
anticipating that the concerned authorities were bent upon for harassing
and intimidating him, he made a request to the concerned Mining
Engineer to conduct an enquiry with regard to the allegations of illegal
excavation. This was also followed by a detailed representation on
14.07.2008, in which he, inter alia, mentioned that the report based on the inspection on 25.02.2008 alleging illegal excavation, was factually
incorrect and that he was prepared to cross examine the witnesses
supporting such imputations. The jurisdictional Mining Engineer,
however, without considering the representation, passed an order on
16.07.2008, inter alia, to the effect that due to illegal excavation an amount of Rs.94,08,000/ - was recoverable from the appellant by way of
cost of minerals involved. This proposal was also approved by the
concerned Superintending Mining Engineer on 15.07.2008. The
appellant/writ -petitioner then filed a revision petition before the Deputy
Secretary, Mines, who remanded the matter to the Additional Director,
Mines, Jaipur for constituting a committee to re -conduct the survey in
her presence. Eventually, pursuant to the order dated 04.08.2009 of this
Court in S.B. Civil Writ Petition No.7000/2009, a Committee was
constituted, which conducted the survey of the area from 03.12.2009 to;