JUDGEMENT
GOVIND MATHUR, J. -
(1.) THIS application is preferred to have a
direction for appointment of an independent arbitrator
to resolve the dispute arising between the parties
under the contract dated 30.7.1996 named as
"Construction of 120 men barracks including sanitary
installation, water supply and drainage for 172 Bn. at
B.S.F. Campus, Karanpur (Rajasthan)".
(2.) THE facts relevant to be noticed are that the applicant, a partnership firm, entered into a
contract with the respondent No.2 on 30.7.1996 for
construction of 120 men barracks including sanitary
installation, water supply and drainage for 172 Bn. at
Border Security Force Campus, Karanpur (Rajasthan). As
per the agreement arrived the work relating to the
contract was to commence on 9.8.1996 and was to be
completed within a period of nine months thereafter.
As per the applicant all necessary raw material,
machines, tents were placed at the site of
construction and the labourers were also engaged, but
no lay out plan was available with the respondents and
that caused non -commencement of the work assigned. The
applicant made request to the respondents to supply
the lay out plan but of no consequence. The
respondents instead of providing lay out plan rescind
the contract agreement under a latter dated 26.5.1997.
A direction was also given to the applicant firm to
deposit the earnest money of Rs.1,00,000/ -. The
applicant being aggrieved by the action of the
respondents mentioned above submitted a notice to the
respondent No.2 on 1.12.1997 to refer the matter to
the arbitrator to initiate arbitral proceedings.
Suffice to mention that clause 25 of the agreement
dated 30.7.1996 provides that all questions and
disputes relating to the meaning of the
specifications, designs, drawings and instructions
mentioned in the agreement and as to the quality of
workmanship or materials used on the work or as to any
other question, claim, right, matter or thing
whatsoever in any may arising out of or relating to
the contract, designs, drawings, specifications,
estimates, instructions, orders or these conditions or
otherwise concerning the works or the execution or
failure to execute the same whether arising during the
progress of the work or after the cancellation,
termination, completion or abandonment, shall be dealt
with through arbitral proceedings. In spite of giving
notice dated 1.12.1997 no arbitrator was appointed by
the respondents, thus, an application was filed by the
applicant before the court of Additional Civil Judge
(Senior Division) Sonepat on 23.6.1998. The
application aforesaid after hearing the parties came
to be dismissed on 16.7.2009 on the count that the
court was not having territorial jurisdiction. After
dismissal of the application the applicant firm
preferred this application before this Court on
19.5.2010.
This Court by order dated 14.12.2010 issued notices to the respondents by noticing the fact that
earlier application under Section 11 of the
Arbitration and Conciliation Act, 1996 (hereinafter
referred to as "the Act of 1996") was filed in the
court of Sonepat and that came to be rejected on
16.7.2009 under the order Anx.25 holding that the said court had no jurisdiction and the application could
have been filed in the State of Rajasthan.
(3.) THE respondents after having service of the notices are contesting the matter mainly on the count
of delay. It is submitted by counsel for the
respondents that the agreement in question was
executed in the year 1996 and the grievance of the
applicant pertains to the year 1997. No reason exists
now to initiate arbitral proceedings for such a stale
dispute.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.