JUDGEMENT
-
(1.) The abovementioned two revision petitions are being disposed of by this
common judgment as in both of them common questions of law and facts are involved ;
Facts of Revision petition No, 1073/2002
(2.) In this revision, an application dated
5-6-2004 was filed on behalf of the petitioner
under Section 151, Cr.P.C. with a prayer that
since award dated 14-8-2003 has been
passed by the Arbitrator in its favour, therefore, the respondent be directed to make
payment of amount of Bank guarantees to
the tune of Rs. 33,91,282/- to the petitioner
immediately along with Interest @ 12% per
annum.
(3.) It arises in the following circumstances :
(i) That tenders were invited by the respondent for construction of health centre
and stadium (Package VI) and the tender
submitted by the petitioner firm was accepted by the respondent and an agreement
between the parties was executed on 26-2-
1998 and the total cost of work as estimated
was about 2.49 crores. As per the contractual conditions, four bank guarantees were
furnished by the petitioner from the Central Bank of India, Kolkata Branch, Kolkata.
(ii) Since a dispute arose between the
parties, respondent terminated the contract
executed on 18-5-1999 and thereafter the
respondent attempted for invocation of the
bank guarantees furnished by the petitioner
firm.
(iii) There was a Clause 25.3(F) in the
agreement to the effect that in case there
was some dispute, the same may be referred
to the sole Arbitrator and in pursuance of
the above Clause, the matter was referred
to sole arbitrator and on 7-8-99, Sh. O. P.
Goel was appointed as sole arbitrator.
(iv) That the proceedings before the sole
arbitrator were going on, the petitioner-firm
submitted an application on 25-3-2002 under Section 17 of the Arbitration and Conciliation
Act, 1996 (hereinafter referred to
as the Act of 1996) asking for certain interim measures of protection in respect to
the bank guarantees furnished by it to the
respondent in connection with the said contract.
(v) After hearing both the parties, through
order dated 23-6-2002, the sole Arbitrator
allowed the application filed under Section
17 of the Act of 1996 by the petitioner -qlaim-
ant in the following manner :
"Keeping the three principles of prima
facie case, balance of convenience, and the
possibility of irretrievable loss, I find that
the justification lies in allowing protection
of the property of the claimants in the hands
of the respondents that is the bank guarantees, as per authorization given to the
arbitrator under Section 17 of the Arbitration
and Conciliation Act, 1996.I, therefore, order that the respondents should preserve
the bank guarantees as detailed in the application as a property of the claimants. I
am simultaneously, providing security to the
respondents by ordering that the claimants
should ensure that they keep the bank guarantees valid and alive till such time the
ftnal award in the disputes under arbitration
with me is issued. Thus, the respondents
shall refrain from invoking the bank guarantees and the claimants shall ensure
keeping the bank guarantees alive and valid till
the final award in the case is issued by the
arbitrator.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.