JUDGEMENT
Prakash Tatia, J. -
(1.) This appeal is against the order dated 23/12/1994
passed by the learned Additional
District Judge No. 1 Jodhpur in Civil
Misc. Case No. 17/93 by which the
learned Additional District Judge
No. 1, Jodhpur dismissed the application
under Section 20 of the Arbitration Act, 1940 filed by the appellant
against the respondent.
(2.) Brief facts of the case are that
the appellant and respondent No. 1
both are Companies incorporated
under the Companies Act, 1956. The
respondent carries on its business of
extracting natural oil/gas and allied
products. The respondent desired to
award a contract for charter-hire of an
on-shore drilling Rig in the region of
Rajasthan. The appellant was one of
the parties who gave the bid for the
said contract. It is alleged by the appellant in his application under Section
20 of the Arbitration Act that before
letter of intent was issued by the respondent, certain meetings took place,
at which the representatives of the
appellant were present and discussions were made for finalising the
terms and conditions which were to be
incorporated in the contract. The
respondent, by telegram dated 30/5/
1990. awarded the contract to the
appellant for the charter hire of one
1400-155 HP on shore drilling Rig to
be deployed in the Rajasthan. By said
letter of intent, the appellant was
required to furnish a performance
guarantee by way of a bank guarantee
of Rs. 98.30 lacs which was done by
the appellant.
(3.) The appellant in para No. 10
of the application under Section 20 of
the Arbitration Act demonstrated the
reasons in support of the appellant's
contention that the contract between
the parties was dependent upon the
regulations of the Government of India
and was also dependent upon the
approval from the various Ministries
and Departments of the Union of India
which were, according to the appellant, were not within the control of
the appellant. The appellant tried its
best to complete the work at his end
and, in pursuance of that, issued
advertisement for purchase of a requisite Rig on 28-4-1990 but no response
was received by the appellant upto
12-6-1990, i.e., for 45 days. The appellant also submitted application to the
Ministry of Industries to obtain capital
goods clearance for the import of a
second hand drilling Rig and an
application was also made to the ICICI
for financial assistance by way of
foreign currency loan for importing the
Rig and another application was made
on 13-9-1990 to the SCIC1 for foreign
currency loan. This way, the appellant
tried to justify that there was no fault
of the appellant at any point of time
and since the appellant duly complied
with all the terms and conditions on
its part entitling it to extension of time
and/or suspension of its obligation
under the contract by reason of the
subsistence of the Force Majeure
conditions and the applicability of the
Force Majeure clause in the said
contract. It is further submitted by the
appellant that the appellant submitted
notice as required under clause 37.4
of the contract stating reasons for
beginning of Force Majeure conditions.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.