JUDGEMENT
-
(1.) This is an arbitration application u/s 11 of the Arbitration and
Conciliation Act, 1996 for appointment of the Sole Arbitrator for
deciding the dispute arising out of contract dated 13.8.2004
executed between the parties, for supply of different type of
papers, which contained Clause 6 wherein it has been mentioned
that all the disputes arising out of the contract and interpretation
thereof shall be decided by the Board of Directors / Administrator
and his decision would be final.
(2.) Counsel for the Applicant submits that the aforesaid Clause 6 is
an arbitration clause and even if this Court comes to the conclusion
that the said Clause No.6 is not an arbitration clause, a direction may
be issued to the respondent to decide the claim of the applicant as
early as possible as has been done by the Supreme Court in Para 6 of
Nav Bharat Construction Co. V. State of Rajasthan and others, 1996 7 SCC 89 after holding in para No.5 that Clause 23 of the agreement
in question in that case that the decision of the Chief Engineer to be
final, is not arbitration clause.
(3.) Counsel for the Non-applicant submits that the aforesaid Clause2
6 is not an arbitration clause as in the said clause, no right of
reference has been given to the Applicant and further, no duty has
been cast upon the Board of Directors or the Administrator to act
either judicially or quasi-judicially while deciding the dispute. Counsel
for the Non-applicant also submits that there is no obligation upon the
Board of Directors / Administrator to take evidence and after hearing
the application to decide the said dispute and further, both the parties
are bound by the said decision and the same must be enforceable in
law. In support of his aforesaid contention, counsel for the Nonapplicant has placed reliance on the Supreme Court judgment in
State of Orissa and others V. Bhagyadhar Dash, 2011 2 WLC(SC)CVL 517, more particularly Paras 3, 3.2, 3.3, 3.4, 3.5 and 3.6. It
would also be appropriate to mention here that under the heading
before Para No.6 the Supreme Court has also prescribed the tests
applied to find out whether they could be termed as arbitration
agreement and similar term where the Superintending Engineer was
given right to decide the dispute about the rate of contract, was held
to be not an arbitration clause from paras 15 to 17.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.