JUDGEMENT
J.C.Verma, J. -
(1.) This revision petition
has been filed by the Union of india, Ministry
of Defence against the order of the District
Judge dated 23.2.1999 whereby the application filed by the repondent under Section 11
of the Arbitration and Conciliation Act, 1996
for appointment of Arbitrator had been
allowed.
(2.) The petitioner is aggrieved against such
appointment of Arbitrator. An agreement was
entered into between the parties for the contract in question and under Clause 7 of such
agreement, the dispute between the parties was
referable to the arbitration. The case of the
respondent is that despite the work having been
done within time, the payment was made in
time.lt was also disputed that the respondent
had not done correct measurement. Demand
was issued to the appellant with request to
appoint the Arbitrator. The Union of india had
not appointed any Arbitrator and a dispute
arose for the payment of Rs. 66,41,500/-.
Notice was issued on 31.7.1997, but no action was taken, therefore, application was
moved to appoint an independent Arbitrator.
(3.) Per contra, the appellant had stated
that full and final payment had been made on
11.6.1994 which was received without any
objection. It was stated as per the condition
No.63 of the agreement after the receipt of
the full and final settlement, no right was left
with the parties to raise any dispute and as
such no arbitrator could have been appointed.
It was also averred that the demand was given
on 13.9.1994 and as such the application was
beyond limitation. As per the appellant the final
bill was made on 28.10 1993 and payment
was made on 11 6.1994 and as such receipt
of any dispute after the period of three years
was beyond limitation.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.