JUDGEMENT
Shiv Kumar Sharma, J. -
(1.) The appellant State of Rajasthan in
the instant miscellaneous appeal seeks to quash the order dated
October 24, 1996 of the learned Additional
District Judge No. 2, Jaipur City whereby award
of the Arbitrator dated September 6,1994 was
made rule of Court and decree in the sum of
Rs. 2.55,752/- was passed together with interest and costs.
(2.) Contextual facts depict that the Public
Health Engineering Department, Government
of Rajasthan (in short the appellant) had invited tenders for supply of A.C. Pressure Pipes
of various size on the terms and conditions
narrated in the tender notice. As many as 24
concerns had participated in the tender. Tenders were thereafter opened on April 10,1985,
wherein the rates submitted by M/s Shree Pipes
Ltd. (in short the respondent) were not found
to be lowest, yet it was decided in the meeting
of the Store Purchase Committee that 25% of
the requirement of AC Pressure Pipes of
150 mm. and above may be awarded to the
respondent at the lowest approved rates being
the respondent Company situated in the State
of Rajasthan. Rate contract was entered into
between the appellant and the respondent and
a condition of 'price fall' and also included in
the terms and conditions of the rate of contract. One M/s Hyderabad Asbestos Cement
Products Ltd., New Delhi which was on rate
contract for supply of AC Pressure Pipes informed the
appellant vide letter dated November 8, 1985 that there
was a downward revision in price and, therefore, they are ready to
supply AC Pressure pipes on a lower rate. On
receipt of the said letter, the appellant had sent
a telegram to the respondent on February 15,
1986, wherein it was clarified that if the respondent Company was agreeable to supply
AC Pressure Pipes on the rates to be approved
by the Government, the respondent may send
its acceptance. In response to the telegram,
the respondent conveyed their acceptance to
supply the goods in pursuance to the condition enumerated in the
telegram and accordingly the appellant issued a supply order vide
their Order No. 231/GS for supply of AC Pressure Pipes and couplings.
While giving the order for supply, the rate quoted therein were at
variance with the rate of contract. The respondent
supplied the material as was demanded by
the appellant but there was some delay in supply of the same.
(3.) During the pendency of the supply of
the material M/s Hyderabad Asbestos Cement
Products Ltd., New Delhi gave the offer to
supply AC Pressure Pipes on lower price at
Jaipur Depot charging only RST. It was given
out that the Government would be having 4
per cent rate difference on the lower side on
account of non-payment of CST. The matter
was considered by the Store Purchase Committee of the appellant in its 100th meeting
and a decision was taken that the rates of
M/s Hyderabad Asbestos Cement Products
Ltd. without CST were to be taken as reduced
rate which were to be offered to the supplier.
Accordingly revised provisional rates were intimated to all Field Officers and suppliers with
direction to make recoveries from suppliers on
account of previous provisional rates allowed
to them for the supplies made on or after January 6, 1986 vide letter dated November 24,
1987. The respondent Company had asked
for a reference to the Arbitrator as dispute arose
after issuance of the letter dated November 24,
1987. Accordingly the matter was initially referred to the Sole Arbitrator Mr. Justice D.P.
Gupta. On his Lordship's sad demise Mr. Justice N.M. Kasliwal, (Retd. Supreme Court
Judge) vide order dated December 13, 1993
was appointed as Sole Arbitrator. The Arbitrator gave award on September 6, 1994 and it
was made rule of the Court vide order dated
October 24, 1996 of the learned Additional
District Judge No. 2, Jaipur City which has
been called in question in the instant miscellaneous appeal.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.