JUDGEMENT
-
(1.) Though the matter comes up on an application filed by the respondents seeking vacation of the ad interim order dated
8/1/2020, looking to the nature of dispute involved and the submissions made, the arguments were finally heard.
(2.) This writ petition has been filed by the petitioner aggrieved against the e-tender for securing service contract at Defence
Laboratory, Jodhpur dated 26/11/2019 and a direction to extend
the contract of the petitioner for another 09 months from the date
of completion of period of 03 months granted through the supply
order.
It is inter alia indicated in the writ petition that the petitioner agency is engaged in providing private security services and is empanelled with the Directorate General Resettlement (DGR).
(3.) The petitioner applied for sponsorship from DGR to participate in the tender process, wherein, ex-servicemen are
employed for the purpose of providing security services and
incidental services at the site at Defence Laboratory. The requisite
sponsorship was accorded to the petitioner.
Invitation for bids to the prospective bidders through limited e-tender was issued by the respondent department for providing security service at Defence Laboratory, Jodhpur. The same was duly submitted, wherein, the petitioner was declared successful. ;