JUDGEMENT
-
(1.) The challenge in the present revision petition is to the order
dated 14.6.2006, whereby in view of the arbitration clause in the
agreement, the matter was referred to arbitration and the suit was dismissed.
(2.) The petitioner was granted a contract for construction of Girls'
Hostel at Talwandi Sabo vide allotment letter dated 5.5.2005. The
conditions of the contract have been appended by the petitioner as
Annexure P.4. Clause 25A of the said contract pertains to disputes and
arbitration. On 27.4.2006, the Executive Engineer of the University invoked
Clause 3(b) of the agreement and the remaining work of the building was
taken over by the University to be carried out in the manner considered
appropriate by it. The said communication addressed by the Executive
Engineer was challenged by the petitioner in a suit for declaration. In the
said suit, an application was filed by the University to refer the matter to
Arbitrator in terms of the arbitration clause in the agreement. The said
application has been allowed vide the order impugned in the present
revision petition.
(3.) The sole argument raised by the learned counsel for the
petitioner is that the letter dated 27.4.2006, has been issued by the Engineerin-
Charge and in terms of Clause 25A of the agreement, the petitioner
cannot seek arbitration unless there is settlement by Engineer-in-Charge.
Since the action has been taken by the Engineer-in-Charge, the petitioner
cannot seek any settlement from such Engineer-in-Charge and, therefore,
the stage of settling dispute by Arbitration, has yet not matured.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.