JUDGEMENT
-
(1.) The petitioner has approached this Court through the present petition challenging order dated March 3,2006 (Annexure P/14) passed by the Haryana State Industrial Development Corporation ( hereinafter referred to as the "Corporation"). The facts which emerge from the record show that the petitioner had applied for an industrial plot measuring 1000 sq. metres and had deposited an amount of Rs. 45,000/- by way of application money on November 16,1996. A letter of intent was issued by the respondent- Corporation on September 8,1997 and plot bearing No. 194, Sector- 3, measuring 525 sq. metres was offered at a price of Rs. 2,36,250/-.
(2.) The petitioner was required to deposit a further sum of Rs. 14,063/- in order to complete 25% of the total price of the plot including Rs. 45,000/- already paid. The petitioner entered into an agreement dated October 1,1997 and made full payment of the consideration amount. A regular letter of allotment was issued to the petitioner on October 22, 1998. There is a dispute with regard to the date on which the possession was actually offered by the respondent-Corporation. Although the Corporation has maintained that the possession of the plot was offered on October 22,1998 but the petitioner maintains that the same was offered on May 21,2002 and actual physical possession was delivered to the petitioner on October 9,2003. As per the terms and conditions of the letter of intent, the petitioner was required to complete construction on the plot in question within a period of three years from the date of offer of possession was made by the respondent-Corporation. The petitioner claims that it had applied for approval of the building plans on November 29,2004 along with the demand draft for an amount of Rs. 10,000/- with scrutiny fee of Rs. 1650. However, the said building plans submitted by the petitioner were not approved by the respondent-Corporation on account of the fact that the petitioner was required to obtain necessary extension for commencement of the construction activity. On account of the failure of the petitioner to complete the construction within the stipulated period, a show cause notice was served upon the petitioner. The petitioner also maintains that on February 21,2006, Divisional Town Planner/HSIDC had granted approval for the building plans submitted by the petitioner. The petitioner claims that construction activities were commenced by the petitioner and the construction had been raised upto the DPC level. The petitioner applied to the Corporation for water connection. However, the petitioner was communicated through a letter dated March 6,2006 that since the plot in question had been resumed on March 3,2006, therefore, water connection could not be considered in favour of the petitioner. It is in these circumstances that the petitioner has approached this Court through the present petition. Before proceeding any further, it may also be relevant to notice that at some stage, on receipt of a show cause notice from the Corporation, the petitioner had also informed the respondent-Corporation that on account of loss suffered by it in the business, the petitioner-firm was unable to continue the industrial activity and, as such, had decided to surrender the plot in question. However, no further action was taken by the petitioner or the respondent-Corporation on the said request of the petitioner.
(3.) At the out set Shri R.K. Jain, learned Counsel appearing for the petitioner has contended that although the petitioner has not been able to complete the construction in terms of the letter of allotment within a period of three years, but if an opportunity is now granted to the petitioner, then he would complete the construction within a period of six months. Learned Counsel has also undertaken that appropriate production activities shall be commenced in the industrial plot within three months of the completion of the construction. Shri Jain has also argued that the entire amount of consideration stands already paid by the petitioner firm and the only default on account of which the plot in question had been ordered to be resumed was the non-construction by the petitioner.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.