JUDGEMENT
-
(1.) By means of the present application filed under Section 11(6)
of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as 'the
Act'), the petitioner seeks appointment of an Arbitrator to adjudicate the
purported disputes and differences which are stated in the petition.
(2.) The petitioner was awarded a contract for the construction of
major bridges consisting of PSC girders on well foundation including
protection work, road work, earth work filling and cuttings and
embankment RCC boxes/slab bridges in approaches and other
miscellaneous and allied works on Goindwal Sahib, Tarn-Taran new B. G.
Rail Link under ADEN/JRC in Jalandhar District. An agreement dated
23.08.2010 was entered into between the parties in respect of the
aforesaid work.
(3.) It is an admitted case that the work was not completed
within the stipulated period. It is not necessary to note as to whether the
contract prolonged because of the reasons attributable to the petitioner
or it was due to the defaults committed by the respondents. The fact is
that extensions were given from time to time by the respondents
reserving right to levy liquidated damages as per the General Conditions
of the Contract. Last extension was granted upto 25.07.2010 by which
date the work was completed in all respects. The petitioner thereafter
sent a notice dated 26.07.2011 stipulating certain claims therein and
requested for appointment of an Arbitrator. However, by that time, the
final bill was not prepared by the respondents. After receipt of the
aforesaid notice, the preparation of final bill was undertaken and then
bill was prepared on the basis of the measurements recorded in the
Measurement Book (M. B. ).;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.