JUDGEMENT
-
(1.) Petitioner has sought appointment of an arbitrator in respect of disputes arising out of an agreement No. CWE/AF CHD/CHD-289/2001- 2002 for Special Repair to Officers Quarters at High Ground, near Chandigarh dated 21.9.2001. Since, the arbitrator was not appointed in terms of the general conditions of the contract, petitioner invoked the jurisdiction of this Court for appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short the 'Act'). this Court vide the order dated 30.3.2007 (Annexure P-5) in Arbitration Case No. 268 of 2006, M/s EMM Enn Associates v. Commander Works Engineer and others appointed Shri Abhay Kumar Sinha, Additional Chief Enginner, Principal Director (Planning), HQ Chief Engineer Chandigarh Zone, 'N' Area, Airport Roard, Chandigarh as a sole arbitrator.
(2.) The said arbitrator gave his Award on 5.1.2008, wherein it was held to the following effect: -
28. And whereas in light of various submissions made by claimant and respondent in writing as well as during hearing and copies of various judgments produced by both the parties it is concluded that: -
(i) The claimant contractor has invoked Arbitration as per Contract Agreement vide letter No. MN/CWE/AF CHD/CHD- 28/2001-02/01/05 dated 23 Feb 2005 after a gap of 2 years and 10 months approx. from the date of signing bill. This is well within limitation and is in order.
(ii) Claimant contractor has received full and final payment against CA No. CWE/AF/CHD/CHD-28/2001-2002 "Special Repair to Officer's Married Quarters at High Ground near Chandigarh" amounting to Rs. 1,06,662/- without any protest or reservation when final bill amount has been received by claimant vide cheque No. J-265296 dated 31.3.2002 for Rs. 106662.00 claimant was not able to produce any document contrary to these facts.
(iii) As per Condition 65 of IAFW 2249 forming part of the contract no further claim shall be made by the contractor (claimant) after submission of Final Bill and these shall be deemed to be waived and extinguished by Union of India.
(iv) Claimant contractor could not produce any documentary evidence to establish an element of coercion or duress during currency of work or submission of final bill and afterwards.
29. In view of Para 28(i) to Para 28(iv) above and provisions of Section 16 of Arbitration and Conciliation Act, 1996, it is concluded that in present case claim of the claimant contractor does not subsist. As each party has defended their own case, each party will bear their own expenses and therefore, nothing is awarded to each party on account of Cost reference.
2. The petitioner filed objections against the said Award, which were dismissed by the Additional District Judge, SAS, Nagar (Mohali) on 2.6.2010. However, appeal against the said order i.e. FAO No. 5211 of 2010, M/s EMM Enn Associates v. Union of India and another preferred by the petitioner was allowed on 21.4.2011. Such order dated 2.6.2010 was set aside and the objections filed by the petitioner were accepted. Petitioner was given liberty to initiate the proceedings under Section 11 of the Act.
(3.) Thereafter, the petitioner invoked the jurisdiction of this Court for appointment of an arbitrator in Arbitration Case No. 87 of 2011 but the same was withdrawn on 1.6.2011 with liberty to call upon the competent authority to appoint an arbitrator in terms of the agreement between the parties, in the first instance.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.