JUDGEMENT
-
(1.) The petitioner-Association has been allotted plots
measuring 450 sq.metres in Industrial Estate Barhi in May, 2007. As
per the petitioner, the respondents were required to take following
steps within a period of two years from the date of offer of
possession:-
"1.Taking over the possession of the plot.
2. Submission of building plan.
3. Placement of orders of machinery and other capital
goods.
4. Financial tie up.
5. Technical and marketing tie-up."
(2.) The petitioner-Association was granted extension to
complete the project upto 10.4.2011. Their grievance is that they had
applied for electricity connection, which has not been provided to
them. Accordingly, as per the petitioner-Association, they would not
be in a position to complete the construction. As per the petitioner,
basic amenities have not been provided. It is not understood as to
how construction is concerned with providing of basic facilities. At
present, notice is only for starting the constructions to implement the
project by 12.4.2011. At this stage, it would not be appropriate to
interfere in exercise of writ jurisdiction.
Dismissed.
(3.) However, the petitioner-Association may be at liberty to
approach the respondents with their grievance.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.