JAIMAL SINGH Vs. PUNJAB STATE ELECTRICITY BOARD, PATIALA AND OTHERS
LAWS(P&H)-2011-7-153
HIGH COURT OF PUNJAB AND HARYANA
Decided on July 06,2011

JAIMAL SINGH Appellant
VERSUS
Punjab State Electricity Board, Patiala And Others Respondents

JUDGEMENT

- (1.) The petitioner challenges the assessment made by the Electricity Board on the ground that the meter installed in the petitioner's premises did not allegedly register the correct quantum of supply and consequently made an additional demand of Rs. 48,450/- along with the bill dated 25.01.1996. The petitioner filed a suit immediately and in terms of the directions issued by the Court for a reference to the Dispute Settlement Committee, the matter was referred to the said Committee for fresh appraisal. The suit was withdrawn when the Settlement Committee held on 11.03.2000 that the meter had been defective and, therefore, the consumption was required to be increased by 100% from the date of installation of the meter namely from October, 1987 upto the date of change of the meter that was made on December, 1995. The assessment made at Rs. 48,450/- was confirmed.
(2.) Learned counsel appearing for the petitioner points out to Section 26 of the Electricity Act, 1910 as amended by Act 32 of 1959 which was applicable at that time. Clause 6 is relevant for our purpose and it is reproduced here as under: Where any difference or dispute arises as to whether any meter referred to in sub-section (1) is or is not correct, the matter shall be decided, upon the application of either party, by an Electrical Inspector, and where the meter has, in the opinion of such Inspector ceased to be correct, such Inspector shall estimate the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time, not exceeding six months, as the meter shall not, in the opinion of such Inspector have been correct; but save as aforesaid the register of the meter shall, in the absence of fraud, be conclusive proof of such amount of quantity; Provided that before either a licenses or a consumer applies to the Electrical Inspector under this sub-section, he shall give to the other party not less than seven days' notice of his intention so to do.''
(3.) As per this provision, if the meter ceased to be correct and there arose a dispute, then the decision would be taken by the Electrical Inspector who shall estimate the amount of the energy supplied to the consumer for a period not exceeding six months. According to him, when the petitioner disputed the same, the Electrical Inspector was bound to issue a seven days' notice of his intention to have an adjudication with reference to the proper functioning of the meter and a unilateral assessment made at Rs. 48,450/- and including the same in the bill was in contravention of the said provision. The Settlement Committee has assessed the duty as recoverable, from the year 1987 when the electric meter was installed. I hold that the procedure adopted by the respondent and the manner of disposal by the Settlement Committee was in contravention of the provisions and Section 26(6) of, the Act and the assessment made was consequently untenable.;