PUNJAB AGRO RICE BRAN EXTRACTIONS LTD. Vs. BANWARI LAL SURESH KUMAR
LAWS(P&H)-2001-1-112
HIGH COURT OF PUNJAB AND HARYANA
Decided on January 24,2001

Punjab Agro Rice Bran Extractions Ltd. Appellant
VERSUS
Banwari Lal Suresh Kumar Respondents

JUDGEMENT

BAKHSHISH KAUR, J. - (1.) THIS order will dispose of CR No. 1796 of 2000 as well. This is a petition under Articles 226/227 of the Constitution of India for holding that the proceedings before the Arbitral Tribunal comprising of Shri A.C. Sharma, Shri S.D.K. Puri and Shri S.R.K. Agnihotri are void ab-initio and nullity as the Tribunal was not constituted in accordance with the law. It is further prayed that the order passed by the Tribunal Annexure P-1 be quashed and the proceedings shall be governed in accordance with the provisions of Arbitration Act, 1940 rather than the Arbitration and Conciliation Act, 1996.
(2.) THE Arbitral Tribunal which was constituted for adjudication of the dispute between the parties, passed the impugned order Annexure P-1 on January 22, 2000, which reads as under :- "4. Arbitral Tribunal has carefully gone into the evidence produced before it and has heard the oral arguments of the parties and hold the unanimous view that :- (i)(a) It was on persistent suggestion/pressurization by respondent No. 1 (PARBEL) that claimant agreed to participate in the settlement of dispute under the new Act i.e. Arbitration and Conciliation Act, 1996 and such a change over is allowed under Section 85 of the said Act. (b) The provisions of this Section do not debar the parties to come under the New Act even after proceedings commenced under the old Act. Further there is no stipulation therein that these provisions will not come into play if arbitral proceedings under the old Act commenced with the intervention of a Court. (ii) The application of the respondent is time-barred under Section 13(2) and Section 16(2) of the Act i.e., it has neither raised objections within 15 days of the appointment of Arbitration Tribunal nor challenged its jurisdiction before filing its written statement of the claim. (iii) Furthermore, respondent (PARBEL) is estopped by its own act and conduct from raising any objection as it continued participating in the proceedings for about 14 months after constitution of the Tribunal and raised objections only on 13.10.1999 just 3 days before 12th hearing in the case and that too as an additional matter while submitting its reply to the application made by respondent No. 2 for deleting its name from arena of the parties. 5. In view of the above findings, application of respondent No. 1 for closing the proceedings forthwith is hereby dismissed." The order has been challenged on the ground that the Tribunal did not appreciate that in the first instance, Shri A.K. Mishra and Shri K.C. Mohindru were appointed as Arbitrators as per order of the Court Annexure P-2 and Shri V.P. Duggal was appointed as Umpire by the two Arbitrators in accordance with the terms and conditions of the agreement. His appointment was intimated to the Court vide Annexure P-5. Thus, these members of the Tribunal had sanction of the Court of law. Shri A.K. Mishra died and Shri K.C. Mohindru withdrew from the Tribunal. Shri S.R.K. Agnihotri and Shri S.D.K. Puri were nominated on their behalf, but their names were not ratified by the Court in place of the Arbitrators initially appointed. These Arbitrators are, therefore, estopped from conducting arbitral proceedings. These Arbitrators had also no authority to appoint the new Umpire, namely Shri A.C. Sharma, as Shri V.P. Duggal was already appointed as Umpire and his appointment was never revoked. The authority of the Arbitrators who had been duly appointed by the Court can be revoked only with the permission of the Court. Similarly, the substitution can be made by the Court alone. It is averred that the Arbitral Tribunal has also erred in holding that as both the parties have requested for adopting the procedure as mentioned in the Arbitration and Conciliation Act, 1996, the arbitration proceedings before the Tribunal shall be governed by the procedure as laid down in the 1996 Act, rather than than the 1940 Act. Similarly, the order of the Tribunal that the objections have not been filed within 15 days of the appointment of the Arbitration Tribunal, challenging its constitution or jurisdiction, is not relevant because this point will come into play when the Court comes to the conclusion that the proceedings are to be governed by the new Act i.e. 1996 Act.
(3.) THE case of the petitioner is that M/s. Punjab Agro Industries Corporation Ltd. - respondent No. 2 promoted a company by the name of Punjab Agro Rice Bran Extraction Ltd. (in short 'PARBEL'), holding the entire paid up share capital of the Company. On 19.5.1982, an agreement was executed between PARBEL and M/s Banwari Lal, Suresh Kumar - respondent No. 1 for construction of a factory and office building and one of the clauses of the agreement was that the dispute shall be referred to three Arbitrators, two to be appointed by each party nominating one Arbitrator. On 19.9.1985, the Punjab Agro Industries Corporation Ltd. - respondent No. 2 sold the company to M/s. Kewal Singh Dhillon and Associates.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.