JUDGEMENT
M.L.Singhal,J. -
(1.) Through this revision,
M/s. Mogul India Construction Company Limited, Palika Bhawan, Sector 13, R.K. Puram,
New Delhi has assailed the order of Additional
District Judge, Kapurthala dated 1.9 1997,
who had dismissed their appeal against the
order of Senior Sub-Judge, Kapurthala dated
19.7.1994 whereby he (Senior Sub-Judge,
Kapurthala) had declined their (M/s. Mogul
India) prayer for the appointment of Arbitrator.
M/s. Mogul India made application under
Section 20 of the Indian Arbitration Act, 1940.
There was contract between M/s. Mogul India
and Indian Railway Construction Company
Limited for fabrication of steel structural steel
work for M/s. IRCON, RCF site, Kapurthala.
Work was allotted on 31.3.1987 and was
required to be completed within 5 months but
the work was actually complete in about 18
months due to failure on the part of Indian
Railway Construction Company Limited to fulfil
the conditions of the agreement. It was alleged
that the Managing Director of Indian Railway
Construction Company Limited, failed to make
timely payments as per agreement for the work
executed at site. Due to the tight financial position
of M/s. Mogul India, the irritated labour
damaged and stole the office equipments, tools
from store including tools issued by the Indian
Railway Construction Company Limited to
them were damaged and stolen. The recovery
of Rs. 18,000/- made from M/s. Mogul India's
bills was illegal on account of damage/loss of
tools due to the irritated labour for non-payment by the Indian Railway
Construction Company Limited. M/s. Mogul India claimed to be
entitled to the payments which they have detailed in the arbitration
application. It was alleged that they are entitled to interest at the
rate of 24% on all the payments from the date
of completion of work i.e. 20.10.1989 to the
date of final payment. It was alleged that there
was arbitration clause in the agreement and,
therefore, the matter in dispute was liable to
be referred to the Arbitrator. The Central
Government should appoint Arbitrator.
(2.) Respondent Nos. 2 and 3 opposed
this application urging that there was no subsisting arbitration agreement between
the parties in respect of contract agreement No.ICRC/KPT/ 124/M/s. Mogul India Ltd. dated
28.4.1987 in view of the accord and satisfaction arrived at between
the parties duly confirmed by the petitioner by issuance of
certificates dated 31.5.1989 and 1.6.1989 followed
by their letter dated 6.6.1989 and they were
receiving payment thereunder. It was also alleged that no legal valid or cognizable dispute
was available with the petitioner. No legal or
valid dispute had been framed by the respondents in view of submission of full ana final/no
claim certificate signed by M/s. Mogul India.
The alleged arrears referred to in para 4 of the
petition is out of contract and the petitioner
had already received full and final payment with
regard to the completion of work. It was admitted that the work
for fabrication and erection of 200 MT steel valued at Rs. 5 lacs was
awarded to the petitioner. Material comprising of steel,
tools, plants consumable and electricity were to be supplied by the respondents
to the petitioner free of costs. Rates quoted
by the petitioner in the agreement were confirmed and no claim for fluctuation in price
was available under Clause 30 of the Contract
Agreement. The petitioner completed work
in November, 1988 though under the contract
it was to be completed by 30.8.1987. There
was no failure on the part of the respondents
to" fulfil any condition of the agreement Recovery of Rs. 17.920/- was made on account
of depreciated costs for loss of Iron's plant etc
by the petitioner and thus the recovery of was
made under para 32.3 of the Contract Agreement. It was alleged that petition was liable to
be dismissed as there was no dispute which
was liable to be referred to the Arbitrator.
(3.) On the pleadings of the parties, following issues were framed :
(1) Whether there is arbitration agreement between the parties and the
matter in suit is liable to be referred
to the Arbitrator ? OPP
(2) Whether the petitioner is estopped
to file the present suit by his act
and contract ? OPR
(3) Whether the petition is liable to be
dismissed for want of notice under Section 8 of the Arbitration
Act? OPR
(4) Relief.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.