JUDGEMENT
-
(1.) This appeal is directed
against the judgment dated 19-7-2003
passed by the learned District Judge,
Khurda at Bhubaneswar in Arbitration
M.J.C. No. 131 of 2002 dismissing the
application filed by the appellants under
Section 34 of the Arbitration and Conciliation
Act, 1996 (hereafter referred to as 'the Act').
(2.) The Government of Orissa entrusted
the respondent the work of strengthening
and widening of Sambalpur-Rourkela Road
(00 km. to 162.931 km). in three packages
and the dispute arose in relation to Package
No. S4 covered under Contract No. III/
92-93/ABD/S 4 dated 30-9-1992. The value
of the contract was Rs. 41,86,46,497/- and
the work was to be completed within 48
months from the date of commencement
with a clause for extension of time under
certain eventualities. The said agreement
contained an arbitration clause vide Clause
No. 67.3. The work commenced on 28-10-1992
and as per the terms of the agreement
it was required to be completed by 27-10-1996.
Extension of time was granted for the
respondent for completion of work on
understanding that the respondent shall not
claim any compensation for delay in
completion of the work. The work was completed
on 31-3-1997 and on 1-6-1997 the respondent issued
a notice to the appellants claiming compensation for loss incurred by it on
the ground that the said appellants did not
fulfil their part of obligations and committed breach of contract by providing
defective drawings, inaccurate survey, delay in
cutting and removing standing trees as well
as acquisition of lands. The appellants rejected
the claim and processed the final bill.
The final bill was signed on 23-9-98 under
protest and the respondent received a sum
of Rs, 44,08,12,410/- without prejudice to
its claim. On 2-11-1998 the respondent
invoked clause 67.3 of the agreement and gave
notice to the appellant and appointed Sri
Tathagat Roy as an Arbitrator from it's side.
As per the terms of the Arbitration clause
the appellant nominated one Sri G. K.
Behera as an arbitrator from their side and
the Ministry of Surface Transfer (Roads
Wing), Government of India nominated Sri
C. N. Ramdas as the Chairman of the
Committee of Arbitrators. Before the Committee
of Arbitrators claim petition was filed containing
16 items of claim. In course of hearing the
claim Item No. 16 was withdrawn by
the respondent. On consideration of materials
placed before the Committee of Arbitrators, Claim Item Nos. 2, 4, 11 and 15 were
rejected and Claim Item No. 1 was allowed
whereas in respect of other items of claims
were partly allowed and a total sum of Rs.
4,06,65,696 with pendente lite and future
interest at the rate of 10% was granted.
(3.) Challenging the aforesaid award
passed by the Committee of Arbitrators the
appellants approached the learned District
Judge, Khurda at Bhubaneswar in an
application under Section 34 of the Act.
Before the learned District Judge the award
was challenged on the ground that the respondent
having given an undertaking not
to claim any compensation for delay
in execution of the work, Claim Item No. 14 could
not have been allowed by the Committee of
Arbitrators. It was also contended that the
award in respect of additional work under
Claim Item Nos. 5 and 8 are hit under Clause
53.1, 53.2 and 53.3 of the agreement. This
ground was also taken on the basis of the
terms of the agreement that the respondent
was required to give notice to the employer
within 28 days after the event giving rise to
the claims. The respondent took a stand that
the undertaking not to claim compensation
for delay in execution of the work was taken
under duress and the same having been
accepted by the Committee of Arbitrators
there is no scope for the Court to interfere.
The learned District Judge on consideration
of the rival contentions of both the parties,
held that the award passed by the Committee of
Arbitrators is not hit under sub-section (2) of
Section 34 of the Act and accordingly dismissed the application.;