JUDGEMENT
ASHIS KUMAR CHAKRABORTY,J. -
(1.) This is an application under Section 11 (6) of the Arbitration and Conciliation Act , 1996 (hereinafter
referred to as "the Act of 1996").
(2.) The facts giving rise to this application are that the petitioner submitted an offer to the respondent for
the purpose of setting up a Coke-oven Gas based Captive
Power Plant at its Integrated Steel Project at Kharagpur.
After considering the said offer, on February 24, 2008
the respondent issued a letter of intent for design,
engineering, supply, construction, testing,
commissioning, trial run and stabilisation of 2x40 MW
power generation station as per the scope and battery
limits to be discussed and decided mutually. The
petitioner accepted the said letter of intent and the
respondent paid Rs.5 crores as a token advance to the
petitioner and the latter also provided the former with a
corporate guarantee for a sum of Rs.5 crores. On May 02,
2008 the respondent issued a formal work order upon the petitioner for design, engineering, supply, construction,
testing, commissioning, trial run and stabilization of
the said 2x40 MW power generation station at a total
price of Rs.252 crores. Annexures 'A' and 'B' to the
said work order stipulated the terms and conditions as
well as the scope of work to be carried out by the
petitioner as well as the terms of payment by the
respondent to the petitioner. Annexure - 'B' to the said
work order contained clauses, inter alia, contemplating
that any disputes or differences arising in connection
with the contract shall be to the extent possible settled
amicably between the parties and if the disputes and
differences cannot be settled amicably the same shall be
referred to arbitration to the arbitrators, each one to
be nominated by the respective parties. In case, the
said arbitrators are not able to settle the disputes by
themselves the matter shall be referred to an Arbitrator
mutually nominated by the parties whose decision shall be
final. Subsequently, however, the respondent reduced the
scope of work to the effect that the petitioner was
required to design, engineering, supply, construction,
testing, commissioning, trial run and stabilization of
1x40 MW power generation station (hereinafter referred to as "the said power generation station") and same was
accepted by the petitioner. Thereafter, the respondent
issued one purchase order dated May 16, 2008 and two
purchase orders both dated May 18, 2008 to the petitioner
for supplying various equipment, materials and spares of
the said power generation station as well as civil
construction work and for erection, testing,
commissioning, trial run, stabilization of the said power
generation station. On November 29, 2011 the respondent
also issued another purchase order to the petitioner for
design, supply, erection, testing, commissioning and
handing over 132Kb which was amended on June 22, 2012 for
Rs.3.30 crore. On January 10,2010 the respondent issued a
letter informing the petitioner of the fresh "price break
up" against supplies of material, civil work and
erection, installation and commissioning, trial run test
and performance guarantee test etc. in respect of the
said power generation station.
(3.) The first purchase order dated May 16, 2008 contemplated that any dispute or difference arising in
connection with the contract shall be to the extent
possible be amicably settled between the parties herein
and if amicable settlement cannot be reached then all
disputes shall be settled by joint arbitration. The
petitioner claims that the respondent committed various
breaches of the said four purchase orders which were
part, parcel and integrally connected and intrinsically
interlinked to the works under the said first purchase
order dated May 16, 2008. According the petitioner, the
communication dated January 9, 2010 issued by the
respondent issuing fresh "price break-up" against
supplies of materials, civil work and erection of the
said power generation station goes to show that the
respondent had awarded the said work to the petitioner
under different purchase orders albeit the work order
remained a single unit.;